An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS RPCSTATUS LAMINATO PLASTICO HPL Roberto Perrino INFN/Lecce Universita’ di Roma Tor Vergata, 07-10-2003

  2. SITUAZIONE GARA Gara ATLAS in delibera G.E. n. 5062 del 11.02.2000 Importo gara = 416 000 000 ITL = 214.8 KEUR Tagli finanziati (5700 pannelli) = 68 400 000 ITL = 35.3 KEUR N. Pannelli = 7674 (Incluse speciali) Area Totale finanziata = 14345 m2 Costo/m2 = 15.0 EUR/m2 Conclusione gara a esaustione della superficie totale: 30/09/2003 - con 277 lastre 2800x1300 che saranno frazionate nel formato BOSB.

  3. Cio’ che resta da fare E’ calcolato +25% di spare.

  4. COSA MANCA ANCORA (EXTRA GARA+25%) BMLG 27 3.2x1.6=138.24 m22440 EUR BMSA 20 lastre 3.2x1.3=83.2 m2 BMSD+BMSE 15 lastre 3.2x1.6=76.8 m2 BMSE 66 lastre 3.2x1.6=338 m28790 EUR BOS 80 2.8x1.3 + 329 2.8x1.3 + 80 2.8x1.3 + 120 1.6x3.2 = 2394 m242260 EUR BOL 1480 2.8x1.3 + 220 3.2x1.6 = 6514 m2 114965 EUR TOTALE = 168 455 EUR + IVA 20% = 202 KEUR Vs. 165.5 KEUR ASSEGNATI

  5. PROBLEMI PASSATI • PRODUZIONE INIZIATA BENE E A BUON RITMO, MA… • SEQUENZA DI STOP PER LE CAUSE PIU’ VARIE • ESORTAZIONE A NON PRODURRE IN ANTICIPO PER NON CAUSARE DANNI DI STOCCAGGIO • PARTITE DI BACHELITE BAGNATA+DEFORMATA • RIGETTO ALTO DI ALCUNE TIPOLOGIE DI GAS GAPS PROBLEMI PRESENTI • INCREMENTO INATTESO DEI COSTI RISPETTO ALLA GARA • CENTRALIZZAZIONE DEL PROGRAMMA DI PRODUZIONE • PRESSIONE A PRODURRE IL PIU’ POSSIBILE … ORA!!!

  6. AZIONI: Ordine tampone immediato per ~500 pannelli, a coprire cio’ che e’ stato di fatto gia’ prodotto per ATLAS oltre-gara + cio’ che e’ necessario produrre a novembre. Far seguire ordini per impegnare il finanziamento di 165.5 KEUR e garantire la continuita’ di approvvigionamento.