SUB-LEMBANGAN : SUNGAI KAMBAU@SG SEDILI BESAR. DAERAH : KOTA TINGGI LAPORAN KEMAJUAN DAN STATUS PELAKSANAAN STATUS SEHINGGA: JUN 2012. SUB LEMBANGAN SUNGAI KAMBAU. Sub2: Sub Lembangan Sg Kemang. KOTA TINGGI. DAERAH KOTA TINGGI 3500 KM2 LEMBANGAN SG SEDILI BESAR

svea
Download Presentation

SUB-LEMBANGAN : SUNGAI KAMBAU@SG SEDILI BESAR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SUB-LEMBANGAN : SUNGAI KAMBAU@SG SEDILI BESAR DAERAH : KOTA TINGGI LAPORAN KEMAJUAN DAN STATUS PELAKSANAAN STATUS SEHINGGA: JUN 2012

  2. SUB LEMBANGAN SUNGAI KAMBAU Sub2: Sub Lembangan Sg Kemang KOTA TINGGI DAERAH KOTA TINGGI 3500 KM2 LEMBANGAN SG SEDILI BESAR 1435KM2 SUB-LEMBANGAN SG KAMBAU 164KM2 SG KAMBAU

  3. PROFIL SUB LEMBANGAN – KAWASAN FOKUS MaklumatSosio-Ekonomi InfrastrukturUtama KAWASAN FOKUS Namajps@komuniti: ZON 5 – SgKambau@SgSediliBesar Lokasi: Kg KambauMukimSediliBesar Koordinat: Sub-lembangan: Sg. Kambau (keluasan 30km2) Panjang 7km2 (Dr Kuala SgPayonghinggakeUluSg) Lembanganutamanegeri: Sg. SediliBesar (keluasan 1435km2) Daerah: Kota Tinggi DUN: Sedili, Parlimen: Kota Tinggi PBT: 1 PBT : Majlis Daerah Kota Tinggi Taman-taman: Tiada Jumlahpenduduk: Nilaihartanah: RM15 / persegi Gunatanah: Pertanian / Akuakultur (70%), HutanSimpanKekal 30% Jambatan JPS

  4. JUSTIFIKASI PEMILIHAN SUBLEMBANGAN (PESTEL) KAEDAH PEMILIHAN SUBLEMBANGAN P – Politik 1. Kg KambaumempunyaikawasanKelapaSawityang luasdansebagainyaterlibatdenganbanjirsejakdahulu E – Economic 1. Kerugianribuan Ringgit darihasiltanaman yang ditenggelami air S – Social 1. Kepadatanpenduduk yang tinggi yang melibatkanbeberapabuahkampung T – Technology 1. KajianPelanIndukTebatanBanjirSg Johor dapatdigunakansebagaipanduanmenyelesaikanmasalah E – Environmental 1. Pencemaransungaiberlakuakibatpembukaantanahdanpenggunaanbajapertanian L – Legal 1. Tiadatindakkanpenguatkuasaanterhadappenceroboh-pencerobohrezabsungai

  5. MASALAH DI sub-lembangan ISU DAN MASALAH DALAM SUB LEMBANGAN • Siapa yang MerasaiImpak : • Kg Kambau

  6. SUB-LEMBANGAN : SUNGAI KAMBAU@SG SEDILI BESAR • DESCRIBE • (PENERANGAN ISU) • Menerangkanmasalahdalamsublembangandenganterperinci • Siapakah yang merasaiimpakmasalahini ? • SiapakahAgensi yang bertanggungjawab? • Apakahtindakan yang pernahdilaksanakan • Adakahmasalahinibermusimatauberpanjangan

  7. BANJIR Isu-isudalam sub-lembangan • Kebun-kebunPertaniandikawasanSgKambauditenggelamiair akibatdarilimpahan air pasangdanbertemudenganhujanlebatdanmengakibatkanbanjir. • Pencerobohantanahdibahagianhulumenyebabkanaliranpuncakberlakudalamtempoh yang singkat. • SistemsaliranPertanian yang tidaksempurnadantidakdiselenggarasecaraberkala.

  8. SUNGAI & KORIDOR ISU-ISU DALAM SUB-LEMBANGAN • Bahagiankuala Sungai mudahdimendapilumpurmanakaladibahagianhuludimendapiPasir. • Sungai KambaujugamempunyaiisupencerobohanRizabdantanahkerajaan • Sungai Kambauadalahsungai yang terlibatdengankawasanPertanianKelapaSawit

  9. SUB-lembangan: SUNGAI KAMBAU@SG SEDILI BESAR • EXPLAIN • (MEMPERJELAS & MEMPERINCIKAN) • Bagaimanamasalahinibermula? • ApaPunca-puncautama? • Siapakahpihakberkepentingan (stakeholder) ? • Masalahmana yang perludiselesaikandahulu ? • Bagaimanakebekesanansistemsaliransediaada? • Apakah data ataupeta yang diperlukan ?

  10. KAWASAN BANJIR DI KAWASAN FOKUS KAWASAN PERTANIAN KG TELOK SG ELOK JERI SG KAMBAU KG TANAH PUTIH KAWASAN PERTANIAN JAJARAN SG KAMBAU

  11. KAWASAN BANJIR DI KAWASAN FOKUS KG TELOK SG ELOK JERI KG TANAH PUTIH KAWASAN PERTANIAN JAJARAN SG KAMBAU

  12. PENGLIBATAN STAKEHOLDERS SENARAI STAKEHOLDER DAN PERANANNYA

  13. PENJELASAN ISU DAN MASALAH ISU ISU BERBANGKIT Cabaran & Kekangan Ketiadaanrizab. Pembangunan yang amatpesat. Masalahutiliti yang merentasparitdanlongkang yang menyempitkansaluran JPS Daerah Kota Tinggikurangkakitangan Sungai Telok Jeri beradadidalamkawasanPertanianKelapaSawit & TanamanKontan MASALAH UTAMA - BANJIR • BanjirdikawasanKebundanladangdi Kg Telokdan Kg Tanah Putihdankawasansekitarnyaberlakusejakdaridahululagi. • Diantarapuncanya : • Air pasangbertembungdengan air hujanlebat • Keadaan Sungai yang menjadicetekakibatdaripadaaliranpasirdanlumpur.

  14. SUB : SUNGAI TELOK JERI@SG SEDILI BESAR • EVALUTE • (MENILAI KAEDAH PENYELESAIAN) • Kenalpastikeperluanmaklumat • Dapatkanmaklumbalasdari Stakeholder • Apakahopsyenpenyelesaian yang ada ? • AnalisisKejuruteraan • Tetapkanskopkerjapenyelesaiankerja • Tentukankeutamaantindakan

  15. INVENTORI MAKLUMAT KAJIAN • Rumusan: • KAJIAN PELAN INDUK SALIRAN BANDAR KOTA TINGGI HSS INTERGRATED SDN BHD • KAJIAN TEBATAN BANJIR SG JOHOR OLEH PERUNDING KNL 2010 MAKLUMAT TAMBAHAN 2. Mendapan Pasir dikuala Sg Telok Jeri MAKLUMAT GIS Peta topo 1:50,000 Peta lembangan –lembangan sungai utama dalam Daerah Kota Tinggi Peta Daerah Kota Tinggi Peta Kawasan Banjir MAKLUMAT YANG DIPERLUKAN Peta digital skala 1:5000 atau 1:10000 Foto udara

  16. ANALISIS KEUTAMAAN TINDAKAN PENYELESAIAN ANALISIS KEUTAMAAN TINDAKAN PENYELESAIAN

  17. SUB : SUNGAI TUAN SEH@SG SEDILI BESAR • PRESCRIBE • (PENGESYORAN STRATEGI/KAEDAH PELAKSANAAN PENYELESAIAN) • Tetapkankaedahpelaksanaankerjapenyelesaian • Terangkanstrategipenyelesaianmasalah • Jadualkanpelaksanaan (jangkapendek/sederhana/panjang) • Jelaskanhasil (outcome)yang dijangka • Mulakankerjajangkapendek (pelaksanaan)

  18. JangkaPendek \ Kerja yang bolehdilaksanakansegeradanmempunyaiimpakserta-merta (1 – 6 bulan) TINDAKAN JANGKA PENDEK

  19. JangkaSederhana \ Kerja yang bolehdilaksanakandalamtempohpertengahan (6 hingga 24 bulan) TINDAKAN JANGKA SEDERHANA

  20. JangkaPanjang \ Kerja yang memerlukanperancangan , pengumpulan data dananalisis yang kompleks (2 tahunkeatas) TINDAKAN JANGKA PANJANG

  21. SEKIAN, TERIMA KASIH