1 / 17

TRD GAS Progress

TRD GAS Progress. Box-S/C Manifolds UG Power Supply. AMS TIM, JSC, 9-Jan-2007, Th. Siedenburg MIT-LNS. TRD Gas System. SUPPLY. CIRCULATION. DISTRIBUTION. POWER. CONTROL. Supply Vessels (Xe, CO 2 ) Transfer Volumes Mixing Vessel. TRD GAS Box-S.

Download Presentation

TRD GAS Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRD GAS Progress • Box-S/C • Manifolds • UG Power Supply AMS TIM, JSC, 9-Jan-2007, Th. Siedenburg MIT-LNS

  2. TRD Gas System SUPPLY CIRCULATION DISTRIBUTION POWER CONTROL

  3. Supply Vessels (Xe, CO2) Transfer Volumes Mixing Vessel TRD GAS Box-S Relief ValveSafety Requirement

  4. TRD GAS Box-C Circulation Pumps Vent Line Pressure Sensors CO2 Spirometer 55Fe Gasgain Monitor Canister

  5. QM GasSystemEM UG-Crate @ RWTH PreTest

  6. QM GasSyst Tests • Nov.06 F. Spada (Rome) G.Rybka (MIT) • UG Script Control implemented ok • Box-C Functional Check ok - 1 Flipper Valve stuck (remove in FM) • - QM Canister Leak fixed (FM ok) • - Spirometer / Gasgain-Monitor off • Dec.06 F. Zhou (MIT) • Box-S Functional Checks ok - V2a, V2b leaky (QM RV mod. – FM ok) - Transfer & Mixing @ 16 bar ok - Kulite sensor DU noisy • Jan.06 J. Hattenbach (RWTH) • Check Gasgain in TRD Modules • Check Circulation-Flow • Prepare QM TRD-GAS TVT

  7. MIT JAN-04-2007 Inspection at ARDE ok Gastightness 1∙10-5 l mbar/s Shipped to MIT Cabeling in preparation Finished by mid-March 07 FM Box-S FM Box-C Replace Flipper-Valve unitwith Check-Valve Unit (RWTH) Assembly at MIT 2 months

  8. TRD Gas Manifolds • Distribute TRD gasflow into 41 segments • Measure gastightness of individual segments • Allow isolation of a segment when leaky • Introduce no additional risk of gas leakage • Safe operation in globally heated TRD

  9. TRD Manifolds • 20 / 16+4 aluminum bodies machined • Flat Viton sealing modified • Production sequence finalized • QM gastight and functional • FM Manifold cabeling received Connectors shipped to Rome UGPS ready in Mar.07 • QM ManifoldSQ tests in Jan.06 FM ready for octagon in Mar.07 QM

  10. UG Power Supply m.d.i. 6031-S28 29.0V ordered m.d.i. 6031-S12 12.5V ordered Controller for m.d.i. DC/DC major effort Would not protect individual UG-boards Define DC/DC Voltages Power On Control for 12/29V Isolate Subsystems Latch-Up Protection Monitor Operation

  11. UG-Electronics Open Item ListSafe 29V for Kulite SensorsSeparate 5V for TubeAmpSeparate 12V for FV/UGPS • Latch-Up Protection for UG-Board Components: • - 54SX 208/32A FPGA • - LM2941S 12V-> 10V LinReg • - TPS7350 5V-> 5V LinReg • - TPS7333 3.3V->3.3V LinReg • - TPS7325 2.5V->2.5V LinReg • - SN65LVDS390 LVDS-Driver • - AD7476 ADC for P-Sensors • - Si4840DY MOSFET Heater/MV Control • - SUB65P06-20 MOSFET Heater/MV Enable • - SUB85N10-10 MOSFET Heater/MV switch • - LM239A Comparator MV Sense • - Si4544DY MOSFET FV • - Si4966DY MOSFET FV • - MAX225EWI RS232 Driver • HI-508 Analog MUX • - AD620BR UGPS Diff.Amplifier • + TRD-GAS P-Sens., TubeAmp, MCA, Spirometer • - EM System working at RWTH • QM System at Rome with new prototype backplane • Schedule: • - QM backplane prod. in Feb. • QM SQ in Mar/Apr. at SERMS

  12. Problem 1Kulite Sensor Supply Current Design: 29V supply directly from backplane 29V-A and -B connected at sensor Loss of redundancy Risk of losing Marotta Valve actuation power Proposal: Diodes and 1kW Resistor at sensor in Box-S Decision needed for FM Box-S wiring at MIT Also twisted pairs needed to reduce noise

  13. Problem 2TubeAmpSupply • 5V shared with RS232 and ADCs • Risk losing only abs.press.sens. • in TRG Gas volume • Proposals • Supply from UGBC-A only • Add separate 5V LinReg • OVC protect. On TubeAmp

  14. Problem 3UGPS Supply 12V shared with Flipper Valves Risk losing FV actuation power Proposal: Add separate 12V LinReg

  15. Simple UGPD Control Without OVC / latch-up protection Keep UG boards and backplane Passive control of 12V and 29V m.d.i. converters Simple board in UGPD – No Controller Delayed power on after 5V on Switched off when 5V off

  16. UG Power Control Board Replace UHVG in UG-Crate Gasgain monitor HV from U-Crate + Provide individual board SSF for 3.3/5V and Control of 12/29V + No modifications of UG-Boards+ No Controller in UGPD– Redesign UG backplane discussed with Capell & Lebedev, W.Karpinski may design, 20k€ required

  17. TRD Integration Schedule Rosengitter tubing & cabeling Nov 06 - Feb 07Manifold design Apr 06 - Jan 07 √Manifold production Dec 06 - Mar 07 Box-S/C EM -> QM upgrade Apr - Oct 06 √QM Gas System Test @ RWTH Nov 06 – Feb 07Define TRD Operation Procedures- Heater Operation - Supply Vessel Filling / ShipmentUG QM Electronics Prod. & Test Apr 06 - Apr 072nd QM UG Backplane for 2 A-only SystemsBox-S/C FM Prod. & Test Apr 06 - Mar 07UGPD Design, Prod. & Test Nov 06 - Aug 07UGPC/UGBP Design, Prod. & Test Jan 07 - Aug 07UG FM Electronics Prod. & Test tbdQM Gas System Install. on Octagon Apr – May 07TRD Cosmics QM-UG FM-U @ AC May - Jun 07

More Related