Cable Installation Status Report - June 6, 2007

Check the status of HF, HE, HO, and HB cables as of June 6, 2007. Includes remarks on required cable changes, wire cutting, and cable ordering.

wmcadory
Download Presentation

Cable Installation Status Report - June 6, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hcal cable installation status, • Prepared by sasha vishnevski, • June 6, 2007

  2. HF- cables

  3. HF+ cables

  4. HE- Far side cables

  5. HE- Near side cables

  6. HE+ Far side cables

  7. HE+ Near side cables

  8. HO-1 Far side cables HO-1 Near side cables

  9. HO-2 Far side cables HO-2 Near side cables

  10. HO+1 Far side cables HO+1 Near side cables

  11. HO+2 Far side cables HO+2 Near side cables

  12. HB cables Not installed • Remarks: • Change of cable DB is needed (in accordance with Sergeev’s request). • Wire cables have to be cut. • 3. Assembly of 4 bundles (from 12) with optical fibers has to be finished. • 4. Laser cables have to be produced.

  13. HO 0 cables Not installed • Remarks: • 1. Wire cables have to be cut. • Ordering of TTC cables (3 pc, with 6 fibers each) has to be done. • Ordering of Calib. Cables (3 pc, with 6 fibers each) has to be done. • Laser cables have to be produced.