1 / 27

Meter Reader 90 Day Working Group Response to the Markets Committee August 2005 Directive

Meter Reader 90 Day Working Group Response to the Markets Committee August 2005 Directive. Presented to the Markets Committee Susan Clary (CMP) and Carmel Gondek (NU) October 17, 2006. MC’s August 2005 Directive to MRWG.

yoland
Download Presentation

Meter Reader 90 Day Working Group Response to the Markets Committee August 2005 Directive

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Meter Reader 90 Day Working GroupResponse to the Markets Committee August 2005 Directive Presented to the Markets Committee Susan Clary (CMP) and Carmel Gondek (NU) October 17, 2006

  2. MC’s August 2005 Directive to MRWG The Markets Committee (MC) requests that the Meter Reader Working Group (MRWG) develop a recommendation(s) for consideration by the MC related to meter data errors that are discovered after the final settlement has been conducted by ISO-NE. (emphasis added) The recommendation(s) should result in both an expected reduction in the occurrence of such data errors and, because it is not possible to eliminate all potential data errors, provide a means to resolve them within the ISO-NE settlement process. The MC requests that the MRWG focus its efforts on stakeholder process changes and improvements that would preferably not result in an extension of the time period required to complete the final billing process. The MC recognizes that changes to Manuals and/or Market Rule 1 may be required to implement any recommendation that is ultimately approved. To the extent that the MRWG develops a recommendation(s) that would require extension of the time period needed for final billing to occur (i.e. a post 90 day resettlement), the MC requests that such a recommendation be vetted with the NEPOOL Budget and Finance Subcommittee prior to presentation to the MC.

  3. Interim Market SettlementsMay 1999 thru February 2003 • Preliminary Hourly Settlement – Preliminary hourly settlement based on data submitted by hour 37 • Interim Settlement – Revised hourly settlements based on revisions to 37 hour data submitted prior to specific deadline within the calendar month • 90 Day Monthly Resettlement – Monthly resettlement based on calendar month MWH values (not hourly). Resettlements conducted for each calendar month based on monthly average rates • Post 90 Day Resettlement – Revised monthly settlements based on revisions to monthly meter data. Resettlements conducted as necessary for each calendar month based on monthly average rates

  4. Standard Market Design SettlementsMarch 2003 - Present • This period is characterized as post-SMD implementation period and does not allow for any post 90 day resettlements • Preliminary Hourly Settlement – Preliminary hourly settlement based on data submitted by hour 37 • Interim Settlement – Revised hourly settlements based on revisions to 37 hour data submitted prior to specific deadline within the calendar month • 90 Day Hourly Resettlement – Final hourly resettlement based on revisions to hourly meter data. Hourly resettlements conducted for each calendar month

  5. Background: April 2004 • MRWG representatives Sue Clary (CMP), Carmel Gondek (NU) and Dave Cavanaugh (ISO-NE) attended the MC meeting to address the MRWG’s concerns regarding post 90 day resettlements • MRWG was concerned that if meter data errors were discovered AFTER the resettlement timeline there was no mechanism (under SMD) by which the Meter Reader could submit the revised data to the ISO, or a mechanism by which the ISO-NE could resettle the market • MC reps collectively stated that if someone was financially harmed as a result of the fact that the market could not be resettled then they could “throw themselves on the mercy of the MC”

  6. Background: July 2004 – September 2005 • A Market Participant (Strategic Energy) discovered a meter data error in its final bill (90 Day Resettlement) • The issue was brought to the attention of the AMR • The AMR attempted to submit corrected data to ISO-NE but ISO-NE could not accept revised meter reads as the 90-day deadline had passed • Participant submitted a request for a billing adjustment (RBA) to ISO-NE, which was denied • With 92.48% support, the MC attempted to remedy error with proposed amendment to Second RNA • Participant informed by ISO-NE that if they followed through with this resolution ISO-NE would contest this at the FERC • Participant withdrew the resolution

  7. Background Continued:August 2005 – August 2006 • August 9, 2005 - The MC issued the MRWG the directive shown on slide #2 • The MRWG developed a special subgroup, known as the MR 90 Day WG, to address the MC’s directive • The new MR 90 Day WG was comprised of representatives of ISO-NE, the Host Participant Assigned Meter Readers, Generators, Suppliers, and Day, Berry and Howard (DBH) • Over the course of the year the MR 90 Day WG has met on a regular basis and has developed recommendations to bring back to the MC

  8. Host Participant Assigned Meter Readers (HP AMRs) Bill Bayard (NHEC) Heidi Blais (PSNH) Charles Carpinella (CMEEC) Dave Chase (NGRID) Susan Clary (CMP) Corrie Cockrell (PSNH) Carmel Gondek (NU) Bob Hardy (NSTAR) Dave Hesketh (NSTAR) Dan McDonald (Unitil) Jim Michaud (UI) Leslie Peterson (PSNH) Susan Romer (NSTAR) Susie Smart (NGRID) Pat Sprague (BHE) ISO-NE Representatives: Cheryl Arnold Eric Banach Dave Cavanaugh Shannon Hann Rachel Likover Chris Parent Denise Rourke Supplier and Generator Sectors Corey Albrecht (WPS) Nancy Chafetz (CES) Bill Darden (Constellation) Natalie DiGrigorio (Constellation) Ivan Kimball (Con Ed) Melanie Ladd (FPL) Jeff Levine (Suez) Richard Schuler (TransCanada) Day, Berry & Howard (as NEPOOL Counsel) Michelle Gardner Scott Myers MR 90 Day Working Group Members

  9. September 2006 • September 19, 2006, MR 90 Day WG’s recommendations were presented to the Budget & Finance Committee (B&FC) • B&FC agreed that the MR 90 Day WG’s understanding of the financial impacts was accurate and did not require changes to the financial assurance policy • B&FC agreed that if a post 90 day resettlement was conducted, affected parties may incur additional financial assurance obligations for the applicable month only (consistent with the current RBA process)

  10. MR 90 Day WG Recommendations • The group has developed recommendations that ultimately comport with the directive from the MC • The recommendations are to: • Enhance the existing 90 day resettlement process to reduce the opportunity for meter data errors • Incorporate a modified RBA process (a Meter Reader Request for Billing Adjustment or MRRBA) which is a one-time post 90 day resettlement that allows correction for meter data errors • This MRRBA would have a fixed, one-time only, 90 day window following the issuance of the bill containing the 90 day resettlement data

  11. Recommendations (continued) • To aid in communicating the details of our recommendations we are sharing the following documents: • The existing 90 day resettlement timeline – Reflects current process • A revised 90 day resettlement timeline – Incorporates new activity which significantly improves the resettlement process by reducing the opportunity for error without extending the timeline and without impacting existing financial assurance requirements • A post 90 day resettlement timelineor Meter Reading Request for a Billing Adjustment (MRRBA) – This timeline allows the correction of meter data errors (via the ISO-NE settlement process) that were not captured in the 90 day resettlement process

  12. Existing 90 Day Timeline

  13. Proposed 90 Day Timeline With Process Improvements

  14. Proposed POST 90 Day Timeline

  15. Eligibility RequirementsPost 90 Day Resettlement • The following eligibility criteria must be met in order to trigger the occurrence of a post 90 day resettlement by ISO-NE • A MWH per month threshold for at least one asset on one or more Metering Domains must be met to trigger the occurrence of a post 90 day resettlement (threshold to be determined) • This trigger is the difference between the meter reading value utilized in the 90 day resettlement process and the meter reading value to be submitted for the post 90 day resettlement • This is an individual asset threshold test • One exception to the applicability of this threshold would apply to any potential meter data issues raised by the asset owner during the 90 day resettlement that could not be fully resolved for the 90 day resettlement

  16. Eligibility Requirements Post 90 Day Resettlement(continued) • The HP AMR must submit a MRRBA letter to ISO-NE no later than Day 90 following the date of the bill containing the 90 day resettlement charges for the affected calendar month • This letter must explain the circumstances for the MRRBA and contain the signature of the HP AMR responsible for the affected Metering Domain(s) • If more than one Metering Domain is affected, the HP AMR must also get the signature(s) of the HP AMR for the other affected Metering Domain(s) • If a written acceptance by both HP AMR parties is not attached to the MRRBA it will not be accepted by ISO-NE

  17. Statistics for Post 90 Day ResettlementMarch 2003 – May 2006

  18. Process Improvements • Proposal incorporates additional process improvements that were deemed appropriate and directly beneficial to the resettlement process • Improvements to the resettlement have included: • Directly Metered Asset Stakeholder Review (May 2005) • Directly Metered Asset Echo Report (Oct 2006) • Profiled Asset Stakeholder Review and Echo Report (Oct 2006) • Ongoing review of ‘issues’ by MRWG for process enhancements to internal business processes (ongoing since 1999) • Monthly meetings with ISO-NE representatives to prioritize issues/needs, etc. (ongoing since 1999)

  19. Important Points for Consideration • What are the primary business reasons for requesting a post 90 day resettlement (MRRBA)? • All other market products can be addressed through the RBA process • This change would allow meter data errors identified after the 90 day resettlement to be corrected • What are some of the causes of meter data errors? • Meter hardware/software failure • Meter hardware/software programming (incorrect data input variables, wiring issues, etc.) • Meter accuracy (calibration issues identified during periodic on-site evaluation/inspection) • Diversion (intentional or unintentional) • EDI/EBT data not processed correctly

  20. Important Points(continued) • If the TOs allocated more money to the metering, data communication and ISO-NE reporting (which would be in addition to the already significant amount allocated to these matters) could they fully eliminate all meter data errors? • No. In New England there are several million retail customer meters and several thousand meters that comprise the network load. Allocating resources to individually review every single hourly value for each and every meter in NE and manually checking all supplier transactions to be sure they all were executed without error would not be a prudent use of resources and would pose significant financial cost burdens to retail customers and/or suppliers with limited benefit

  21. Important Points(continued) What Can Be Done to Address Meter Data Issues? • Facilitate stakeholder review and input to settlement data • Continue to review and incorporate AMR best practices • Continue to work collaboratively with ISO-NE to identify additional tools and processes designed to help prevent, identify, and/or resolve issues more readily (i.e. PTF tie line review, etc.)

  22. Do the MR 90 Day WG Recommendations Directly Comport with the MC Directive? • Yes, the MR 90 Day WG recommendations comport with the MC directive as follows: • The MR 90 Day WG was directed to provide a recommendation that results in an expected reduction in occurrence of data errors • The recommendation for enhancements to the 90 day resettlement accomplishes that objective • The MC’s directive recognized that not all errors could be eliminated and asked the group to provide a means to resolve them within the ISO-NE settlement process • The recommendation provides, through a post 90 day resettlement, a means to resolve meter data errors that were not possible to eliminate during the 90 day resettlement

  23. Do the MR 90 Day WG Recommendations Directly Comport with the MC Directive?(continued) • The MC’s directive requested that the group focus its efforts on stakeholder process changes and improvements that would preferably not result in an extension of time required to complete the final billing process • The recommendation for enhancements to the 90 day resettlement include stakeholder process improvements • The recommendation for a post 90 day resettlement, or MRRBA, would result in an extension of time for final metered data billing only for months that an MRRBA is issued -- this falls well within the existing timeline for final billing of other market products (via the existing RBA process) • The recommendation for a post 90 day resettlement includes stakeholder review of all revised metered data

  24. Does the MR 90 Day WG Recommendations Directly Comport with the MC Directive?(continued) • The MC’s directive requested that if the group developed a recommendation that would require an extension of the time period needed for final billing to occur (i.e. a post 90 day resettlement) that such a recommendation be vetted with the B&FC prior to presentation to the MC • This objective was satisfied at the September 19, 2006, B&FC meeting

  25. Why does the MR 90 Day WG believe their recommendations are the best approach? • Meets the needs of the Market Participants represented in the MR 90 Day WG • Is consistent with the desires of the Market Participants (e.g. when the issue of a post 90 day resettlement for Strategic was brought to the MC it was supported with a 92.48% vote) • These changes put meter data errors on the same footing as other billing issues • The existing RBA process corrects for all other market products (excludes metered data corrections) • The recommendations of the MR 90 Day WG would correct this oversight and give meter data corrections the same attention that other billing errors receive

  26. Why does the MR 90 Day WG believe their recommendations are the best approach? (continued) • Corrects meter data errors in the most accurate manner possible • In order to capture the financial impact of a meter data correction, the markets must be resettled • ISO-NE is the only entity authorized and capable of performing financial resettlements between Market Participants • Provides the similar recourse that meter data errors had pre-SMD • The recommendation for a post 90 day resettlement has finality as it does not include a continuous 90 day RBA cycle contained within the existing RBA process • The existing RBA process contains a continuous time loop provision which poses considerably greater financial risk than the MRRBA process being proposed

  27. Next Steps and Proposed Schedule • The MR 90 Day WG requests permission from the MC at the October meeting to allow the MR 90 Day WG to develop, with the assistance of NEPOOL Counsel and ISO-NE, red-lined documents reflecting necessary tariff and manual revisions that would be needed to support these recommendations • Proposed schedule: • MR 90 Day WG representatives to return to the MC in November 2006 to present and discuss the red-lined documents • MC to vote on MR 90 Day WG Proposal in December 2006 (or a later MC meeting, as appropriate)

More Related