1 / 18

Data Communications Program

Data Communications Program. DCIT Update MEM ATCT DCL Trials. To: DCIT Plenary From: Matt Maki Date: 09.26.2012. Agenda. DTAP Development Status: DTAP Development/Milestone Deliveries Trials OT&E Results DTAP PTR Status MEM DTAP Equipment Installation Status

afia
Download Presentation

Data Communications Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Communications Program DCIT Update MEM ATCT DCL Trials To: DCIT Plenary From: Matt Maki Date: 09.26.2012

  2. Agenda • DTAP Development Status: • DTAP Development/Milestone Deliveries • Trials OT&E Results • DTAP PTR Status • MEM DTAP Equipment Installation Status • On-going/Completed Trials Activities Status: • Trials FTI/ISSM Provisioning • DTAP Certification • Trials FDIO Test NCP • MEM Training and Procedures

  3. DTAP Development Status

  4. DTAP Milestone Deliveries • SE2020 Contract Deliverables/DTAP Development On-going: • B2 DTAP currently undergoing Functional Testing in FAATC Data Comm lab • Boeing/Airbus and WJHTC bench avionics being utilized for the testing • B1 Regression testing part of current B2 testing • B3 (UM80, Domestic DB) scheduled for 10/1 delivery • Current B2 HIGH level PTRs fixed • B4 (FDIO) scheduled for 10/23 delivery • B5 (UM83, **UM79 Initial) scheduled for Nov. delivery • Working on Thales to provide this delivery sooner • Actual Baseline/functionality deliveries being finalized with the FAA CO and ITT

  5. OT&E Testing – PTR Status • OT&E Testing Successfully Completed (Sept 11-13): • Very positive feedback from participating MEM/EWR controllers (3 from each site) • ATL controllers did not attend (human resource constrained) • Multiple hands on test scenarios provided to each controller • Test Data/feedback documented for review and action • CHI change request coming out of the testing • MITRE Report created • DTAP Functional PTR Documentation: • PTRs categorized as High, Medium, Low status • Weekly review of open PTRs with Thales • Current B2 High Level PTRs planning for fix in B3

  6. DTAP Test and MEM Trials Timeline

  7. DCL Trials – MEM Timeline (updated: 9/14/2012) DTAP 1&2 setup/prep Tech Center DTAP E-E Functional Testing SAT at MEM pDTAP and Update Video crew @ Tech Center event (Sept. 13) Video crew @ MEM event (Sept. 24) AFN and CPDLC connect with Boeing event (July 31, Aug 3, 7, 11) DCL & AFN attempt with DCIT aircraft pre-arranged event # 1 (Aug 28, 29 & 30) Conduct MEM Training AFN, DCL, Revisions with DCIT aircraft event # 2 (Sept. 25, 26 & 27) AFN and CPDLC connect with Airbus event (Aug 6-8) Dry Run & Prep OT&E Sept 10-14 Oct 29 – Nov 10 Controllers early look & feel (Aug. 29) DTAP 2 setup/install&checkout @ MEM (B5) Nov 30 Func. Regression & Operational OT&E SAT Oct 15-25 (B3) Oct 1 (B1) Aug 17 (B2) Sept 3 (B4) Oct 23 May 10 Aug 22 Sept 7 Sept 14 Sept 17 Nov 12 Trials Start • Controller OT (Prep / Dry Run & Conduct) • System test case / bench avionics + TC aircraft • System test case / Boeing air lab • System test case / Airbus air lab • System test case / DCIT aircraft • Error conditions / failover • PTR fixes / regression • 8/23/1012: Security Assessment • Regression with B2 (in lab) • Regression with B3 (Oct 1 in lab) • Regression with B4 (Oct 23 in lab) • DTAP Test Report • Install & checkout • MEM / FDX Training • SAT sub_test cases final • SAT sub_test cases functional testing/ FedEx aircraft • E-E Operational scenarios based on DCIT doc / Live aircraft • Error conditions / failover in field • 9/27/1012: Security Assessment • Regression with B4 (in lab & in field) • SAT Test Report • pDTAP / HADDS vin box test • pDTAP / HADDS via FNTB Failover / Rev # test • pDTAP / HADDS / CSP Interface via FNTB + bench Avionics • pDTAP (applicable reqs/VRTM) testing with bench avionics • pDTAP testing via Boeing + Airbus air labs • PTR fixes / regression • Test Cases document final • pDTAP Quick Look Report (B2) = Adds UM79, AOC DC (no ack) (B1) = CAF, Revised DCLs other than route, CHI, AFN (B5) = Adds UM83 (B3) = Adds UM80, AOC DC ACK (B4) = Adds FIDO

  8. MEM DTAP Installation Results

  9. DTAP 17” Display Installed at MEM

  10. DTAP Pre-Installation Work – Conducted Week of 8/28 150’ Conduit for FDIO Fiber Basement and 12th Fl Fiber Converters

  11. DTAP Installed in 12th Fl Rack (9/17) DTAP FDIO Serial Converters CWP/Maint Display/Keyboard DTAP[ Switches CAT5 cables to be replaced with shorter cables DTAP Servers DTAP PCs UPS UNITS

  12. On-Going/Completed Trials Activities

  13. Trials FTI/ISSM Provisioning Update • Two physical circuits installed at MEM (9/6 – see next slide): - Trials team installed all Fiber/CAT6 to FTI demarc (8/28) • Circuits cannot be Activated until ISSM Trials Authorization package approved and FTI paperwork complete: • ISSM to MEM for testing 9/27 • Final authorization completion planned in early October • Circuit activation challenge date mid-Oct • All ISSM requested documentation sent for review 9/17 • FTI Operations paperwork/approvals being worked on parallel ISSM track: • DC PO/NEMC MOA (Data Comm PM signing pending) • IP SUP form processing – network configuration work • CSP coordination for connectivity

  14. Dual FTI 128k Trials Telco Installed

  15. DTAP Certification • DTAP requires Tech Ops certification: • FTI activation approval can’t proceed until certification parameters documented • Tech Ops officials to meet with DC PO and Thales on 9/26 to review DTAP functionality and certification of service procedures • Draft Operator Manual/Cert Procedure complete for review • Final documentation challenge completion date early Oct

  16. Trials FDIO Test NCP • Additional Test NCP submitted : • Create a MEM FDIO/PCRCU Echo Port for DTAP to filter out Rev # data • CMRT baselined – NAS CCB assignment pending

  17. MEM Training and Procedures • MEM Training and Procedures complete: • Basis for OT&E last week • MEM DTAP Training scheduled Oct 29–Nov 10, 2012 • SAT scenario/procedures development on-going: • MEM SAT on track for mid/late-Oct • SAT dependent on FTI activation

  18. Questions ? KMEM

More Related