Data Communications Program DCIT Update MEM ATCT DCL Trials To: DCIT Plenary From: Matt Maki Date: 09.26.2012
Agenda • DTAP Development Status: • DTAP Development/Milestone Deliveries • Trials OT&E Results • DTAP PTR Status • MEM DTAP Equipment Installation Status • On-going/Completed Trials Activities Status: • Trials FTI/ISSM Provisioning • DTAP Certification • Trials FDIO Test NCP • MEM Training and Procedures
DTAP Milestone Deliveries • SE2020 Contract Deliverables/DTAP Development On-going: • B2 DTAP currently undergoing Functional Testing in FAATC Data Comm lab • Boeing/Airbus and WJHTC bench avionics being utilized for the testing • B1 Regression testing part of current B2 testing • B3 (UM80, Domestic DB) scheduled for 10/1 delivery • Current B2 HIGH level PTRs fixed • B4 (FDIO) scheduled for 10/23 delivery • B5 (UM83, **UM79 Initial) scheduled for Nov. delivery • Working on Thales to provide this delivery sooner • Actual Baseline/functionality deliveries being finalized with the FAA CO and ITT
OT&E Testing – PTR Status • OT&E Testing Successfully Completed (Sept 11-13): • Very positive feedback from participating MEM/EWR controllers (3 from each site) • ATL controllers did not attend (human resource constrained) • Multiple hands on test scenarios provided to each controller • Test Data/feedback documented for review and action • CHI change request coming out of the testing • MITRE Report created • DTAP Functional PTR Documentation: • PTRs categorized as High, Medium, Low status • Weekly review of open PTRs with Thales • Current B2 High Level PTRs planning for fix in B3
DCL Trials – MEM Timeline (updated: 9/14/2012) DTAP 1&2 setup/prep Tech Center DTAP E-E Functional Testing SAT at MEM pDTAP and Update Video crew @ Tech Center event (Sept. 13) Video crew @ MEM event (Sept. 24) AFN and CPDLC connect with Boeing event (July 31, Aug 3, 7, 11) DCL & AFN attempt with DCIT aircraft pre-arranged event # 1 (Aug 28, 29 & 30) Conduct MEM Training AFN, DCL, Revisions with DCIT aircraft event # 2 (Sept. 25, 26 & 27) AFN and CPDLC connect with Airbus event (Aug 6-8) Dry Run & Prep OT&E Sept 10-14 Oct 29 – Nov 10 Controllers early look & feel (Aug. 29) DTAP 2 setup/install&checkout @ MEM (B5) Nov 30 Func. Regression & Operational OT&E SAT Oct 15-25 (B3) Oct 1 (B1) Aug 17 (B2) Sept 3 (B4) Oct 23 May 10 Aug 22 Sept 7 Sept 14 Sept 17 Nov 12 Trials Start • Controller OT (Prep / Dry Run & Conduct) • System test case / bench avionics + TC aircraft • System test case / Boeing air lab • System test case / Airbus air lab • System test case / DCIT aircraft • Error conditions / failover • PTR fixes / regression • 8/23/1012: Security Assessment • Regression with B2 (in lab) • Regression with B3 (Oct 1 in lab) • Regression with B4 (Oct 23 in lab) • DTAP Test Report • Install & checkout • MEM / FDX Training • SAT sub_test cases final • SAT sub_test cases functional testing/ FedEx aircraft • E-E Operational scenarios based on DCIT doc / Live aircraft • Error conditions / failover in field • 9/27/1012: Security Assessment • Regression with B4 (in lab & in field) • SAT Test Report • pDTAP / HADDS vin box test • pDTAP / HADDS via FNTB Failover / Rev # test • pDTAP / HADDS / CSP Interface via FNTB + bench Avionics • pDTAP (applicable reqs/VRTM) testing with bench avionics • pDTAP testing via Boeing + Airbus air labs • PTR fixes / regression • Test Cases document final • pDTAP Quick Look Report (B2) = Adds UM79, AOC DC (no ack) (B1) = CAF, Revised DCLs other than route, CHI, AFN (B5) = Adds UM83 (B3) = Adds UM80, AOC DC ACK (B4) = Adds FIDO
DTAP Pre-Installation Work – Conducted Week of 8/28 150’ Conduit for FDIO Fiber Basement and 12th Fl Fiber Converters
DTAP Installed in 12th Fl Rack (9/17) DTAP FDIO Serial Converters CWP/Maint Display/Keyboard DTAP[ Switches CAT5 cables to be replaced with shorter cables DTAP Servers DTAP PCs UPS UNITS
Trials FTI/ISSM Provisioning Update • Two physical circuits installed at MEM (9/6 – see next slide): - Trials team installed all Fiber/CAT6 to FTI demarc (8/28) • Circuits cannot be Activated until ISSM Trials Authorization package approved and FTI paperwork complete: • ISSM to MEM for testing 9/27 • Final authorization completion planned in early October • Circuit activation challenge date mid-Oct • All ISSM requested documentation sent for review 9/17 • FTI Operations paperwork/approvals being worked on parallel ISSM track: • DC PO/NEMC MOA (Data Comm PM signing pending) • IP SUP form processing – network configuration work • CSP coordination for connectivity
DTAP Certification • DTAP requires Tech Ops certification: • FTI activation approval can’t proceed until certification parameters documented • Tech Ops officials to meet with DC PO and Thales on 9/26 to review DTAP functionality and certification of service procedures • Draft Operator Manual/Cert Procedure complete for review • Final documentation challenge completion date early Oct
Trials FDIO Test NCP • Additional Test NCP submitted : • Create a MEM FDIO/PCRCU Echo Port for DTAP to filter out Rev # data • CMRT baselined – NAS CCB assignment pending
MEM Training and Procedures • MEM Training and Procedures complete: • Basis for OT&E last week • MEM DTAP Training scheduled Oct 29–Nov 10, 2012 • SAT scenario/procedures development on-going: • MEM SAT on track for mid/late-Oct • SAT dependent on FTI activation
Questions ? KMEM