An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters’ Meeting December 03, 2012

  2. Shutdown 2012 • Machine Status: • RFQ commissioning : Beam into Linac starting November 14th. • NTF Scheduled for Patient Treatment week of December 10th • TeV & Muon Rings – Partially available for tours with approval and appropriate training • Site is currently being powered from Master SubStation & KautzRoad SubStation

  3. Power Outages – MSS Bypass • Booster Tower East • November 26th work began and lasts ~2.5 weeks • Booster East parking compromised • Main Ring road was closed from 11/26-30, and will be closed again 12/12-14. • Booster Tower East & West • Saturday, December 8th @ 0700-1530 • Booster Gallery, Towers, and Tunnel • Perform annual maintenance • Booster Tower East • Saturday, December 15th @ 0700-1900 • Booster East Gallery, Towers, and Tunnel • Tie in new switch at A0 and switch pad

  4. Power Outages – MSS Bypass • High Intensity Lab (HIL) Oil Switch • December 17thfor ~ 2 weeks • Will be running house power off a generator • Impacts HIL & PW8 • NS7 Oil Switch • December 20th for ~ 2 weeks • Will be running house power off a generator • Impacts – NS7 Service Building and Adjacent Enclosures (NM2, NM3) • NS1 Oil Switch • January 18th for ~ 2 weeks • Will be running house power off a generator • Impacts – NS1 Service Building and Adjacent Enclosures (N01, NM1) • MS1 & MS2 • January 31st for ~ 2 weeks • Will be running house power off a generator • Impacts – MS1 & MS2 Service Buildings and Adjacent Enclosures (M01, M02, & M03) • PS1 Oil Switch • February 20th for ~ 2 weeks • Will be running house power off a generator • Impacts – PS1 Service Buildings and Adjacent Enclosures (P01). TSB?

  5. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html ANU - http://www-cons/ Proton Source -http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html