An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters MeetingPIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014

  2. PIP Report 3 L2 tasks 9 L3 tasks 31 L4 tasks 30% Linac 70% Booster Ongoing Complete F.G. Garcia AEM - PIP Report 10/06/2014

  3. Linac

  4. PIP - Linac 200 MHz RF Power System • Modulator Upgrade • 35kV, Marx-topology modulator • Progress made on various fronts • Enclosure design complete and near delivery • Gate driver circuit board design/layout done • Short circuit testing continues • Successful designand tests, with available end-of-year funds procure the long-lead items for the full voltage modulator • HLRF – SBK201 • Successful CDR review early July • Focus now shifted to drafting & purchase of long-lead items F.G. Garcia AEM - PIP Report 10/06/2014

  5. PIP - Linac Accelerator Physics • Laser Notch • Internal review carried out early August • Readiness for vacuum cavity / optical cavity installation during shutdown Assembly at lab area Assembly installed RIL beam Laser port F.G. Garcia AEM - PIP Report 10/06/2014

  6. PIP - Linac Utilities Original L1 sub-station • Power distribution (Dec’11-Sept’14) • L1 transformer fully installed • 13.8kV to 480Y/277V • Better heat loss (80C vs 115C) • Low voltage breakers, trip control and instr. • What will become of the removed equipment? • Transformer will be kept as sparefor Linac • additional 2 other old-style transformers in use • Breakers & primary switch will be rebuilt and tested – spares L4 task complete! July’14 Sept 24 ‘14 Sept 17 ‘14 F.G. Garcia AEM - PIP Report 10/06/2014

  7. PIP - Linac Utilities • LCW system • Dual temp. system • Replace cooling provided by EOL DTW piping and fan coil units to a rooftop AC unit • Contract awarded and pre-meeting conducted • Gallery work starts Oct10th • CUB 55 LCW backup pump • Extensive delay • Overran in costs forced the project to be restructure to a FP rather T&M • Process complete in time for the shutdown • Job still has not started! • Vacuum upgrade • Turbo pumps (shutdown’14) • Original pumps in service since day-one • Belt driven / oil reservoir • Heavy, big, replacement parts no longer available • New pumps are sealed clean bearings, compact, high speed, freq. drive control L4 task complete! F.G. Garcia AEM - PIP Report 10/06/2014

  8. Booster

  9. PIP - Booster RF Anode & Bias Supplies • Anode Supplies • Goal: install both supplies during shutdown 2014 • Delays in the delivery of long lead items prevented this task to be complete • AD/EE continue to make progress with assembly • Supplies may be built but not tested by the end of the shutdown • Await for opportunistic shutdown next year to install • Bias Supplies • Scope of work:Replace transformers, re-plumbing and re-wiring for 15 Hz operation Current Situation East gallery: 100% complete West gallery: 10% complete F.G. Garcia AEM - PIP Report 10/06/2014

  10. PIP - Booster RF Cavity & Tuner Refurbishment • Work progressing well with the cavity refurbishment • Scope of work: refurbish all 19 cavities in Booster • Up to now, 11 cavities fully refurbished and re-installed in tunnel • Additional cavity (#20) installed prior the shutdown • Cavity built from leftover parts Current Situation • Cones are bottleneck • Time consuming to rework a used cone • 10 step process F.G. Garcia AEM - PIP Report 10/06/2014

  11. PIP - Booster Notch system • Scope of Work: Reconfigure and replace notch kickers & corresponding high voltage system for faster rise/fall time 3 bucket notch Current Situation • Complete installation of • 6 “short” kicker magnets & corresponding high voltage system • redesigned S12 spool piece • improve aperture at downstream of notch kickers (~10%) • standard Booster BPM’s pickup plates proved to be aperture restriction Short kickers beam F.G. Garcia AEM - PIP Report 10/06/2014

  12. PIP - Booster Radiation Shielding • Scope of Work: Revised Booster shielding assessment to allow high intensity operations. • Present SAD allows for 1.8E17 p/hr • Above ground radiation protection • Practical limit determined by the array of detectors spread around the ring • 50+ interlocked detectors placed above ground at specific locations covering all loss points • Tunnel radiation protection • Overall loss rate limited by the “watt meter” – 525W & • Local control loss possible with array of 60+ BLMs along the tunnel • During the shutdown, 8 TLM’s installed in Booster tunnel • High loss points: Injection, extraction, collimator, notch regions • Beam tests to characterize system F.G. Garcia AEM - PIP Report 10/06/2014

  13. PIP - Booster Utilities • Power distribution • Transformers • First transformer replaced 09/27 (west side) • Problems with the breaker will prevent the installation on the east side this shutdown • Vacuum upgrades • Turbo pumps • All pumps on-hand • Auxiliary cables and relay rack work moving along • Pump installation progressing well • Unlikely to complete this shutdown BWG - transformer F.G. Garcia AEM - PIP Report 10/06/2014

  14. PIP PIP-II adjustments Meetings and discussions began to adjust PIP to PIP-II F.G. Garcia AEM - PIP Report 10/06/2014

  15. PIP - Conclusions • PIP continues to make positive progress towards its goals • Linac • Lots of progress made on the 200 MHz RF system • First step completion of R&D project to create a notch within linac beam pulse using laser system • Completion of two L4 tasks during shutdown 2014 • Vacuum system • Power Distribution • Booster • >50% cavities refurbishment complete • Complete installation of BW house transformer • Setup complete for TLM’s beam tests run • Complete installation of short kicker magnets for notch creation • PIP plan adjustments for PIP-II • Discussions started between PIP and PIP-II to redirect and modify existing PIP activities to line up with PIP-II program F.G. Garcia AEM - PIP Report 10/06/2014