1 / 7

All Experimenters Meeting PIP Report

All Experimenters Meeting PIP Report. William Pellico on behalf of PIP team 4/7/2013. PIP Report. 3 L2 tasks 9 L3 tasks 31 L4 tasks. 30% Linac 70 % Booster. Ongoing Complete. PIP - Linac 200 MHz RF Power System.

neola
Download Presentation

All Experimenters Meeting PIP Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters MeetingPIP Report William Pellico on behalf of PIP team 4/7/2013

  2. PIP Report 3 L2 tasks 9 L3 tasks 31 L4 tasks 30% Linac 70% Booster Ongoing Complete W. Pellico AEM - PIP Report 04/07/2014

  3. PIP - Linac 200 MHz RF Power System • Modulator Upgrade - 35kV, Marx-topology modulator to drive triode (or SBK) • AD/EE complete testing with 9 cells Square Wave Triangle Load Voltage (Green) Current Status: • Finish 9-cells short circuit response • Build interleaved regulator for different stage • Building 25 cells modulator – capable of running LRF1 • Possible FY14 Shutdown Install in RF1 – big reach  W. Pellico AEM - PIP Report 04/04/2014

  4. PIP - Linac Laser Notcher System • R&D project to build a laser system to create the notch within a linac beam pulse @ 750 keV • remove the notch creation outside Booster tunnel reducing activation • 3D model of optical cavity to test design Optical cavity to be installed during shutdown 2014  W. Pellico AEM - PIP Report 04/04/2014

  5. BoosterRF system • New cavities • Efforts continue on developing a model of the existing Booster cavity • Full 3D model with most of the details incorporated • Temperature measurements done on RF10 to assist in modeling – help confirm our model/heating design • Perpendicular Cavity • Recent design looks promising – working on fitting solenoid and PA to cavity model • New ferrite cores • Recent high-mu ferrite cores from vendor look good!!! • Working with vendor to procure enough to build a complete tuner • Plan to test one tuner and then start building tuners this summer W. Pellico AEM - PIP Report 04/04/2014

  6. BoosterRF system • Cavities Refurbishment • 10 of 19 cavities have been refurbished Stats: Last refurbishment : 5 wks (repair of a refurbished cavity) Refurblast 3 cav. : 9.8 wks * Cones and tuners were available BRF 1,3,5,6,7,8,11,15,17 Booster Cavity Work Refurbished (15Hz) Cavity Removed Courtesy: K. Gollwitzer W. Pellico AEM - PIP Report 04/07/2014

  7. PIP - BoosterRF system – Anode and Bias Power Supply • Anode Bias Supply • Design specifications complete • Hardware ordered and bid process ongoing • Plan: install both supplies during shutdown 2014 • Bias Power Supply • Slow start on first supply, complete Mar’14 • Labor limitation, delay with materials, consensus on final layout • Ongoing work on update of transformers, heat sink & SCRs • Intensive labor work • Addition of 2 techs expedited the process • Expect to complete in FY15 Mar’14 W. Pellico AEM - PIP Report 04/07/2014

More Related