1 / 22

Spreader/Recombiner Dipoles and Layout, & Installation Labor Preliminary Design and Safety Review

12GeV Upgrade - Beam Transport. Spreader/Recombiner Dipoles and Layout, & Installation Labor Preliminary Design and Safety Review. Spreaders & Recombiners Beam Transport Michael Bevins May 30, 2007. Outline. Introduction & Scope Requirements & Specifications Beam Transport Layouts

Download Presentation

Spreader/Recombiner Dipoles and Layout, & Installation Labor Preliminary Design and Safety Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation LaborPreliminary Design and Safety Review Spreaders & Recombiners Beam Transport Michael Bevins May 30, 2007

  2. Outline • Introduction & Scope • Requirements & Specifications • Beam Transport Layouts • Safety Considerations • Cost Estimates • Risk Assessment • Summary

  3. Introduction & Scope • The 12GeV upgrade requires extensive modifications to the spreader and recombiner regions of the machine • These are the most congested regions in the beam transport system • The latest and greatest layouts for each of the five spreader & recombiner regions will be presented today along with cost estimates • We expect these layouts to continue to evolve as we work with CASA to minimize the number of interferences as a result of beam transport geometry changes • Cost and installation labor estimates that will be discussed today were developed based on layouts available in March • Layouts have continued to be refined • Detailed design of these regions is scheduled to begin early next year and continue into 2009

  4. Requirements & Specifications Same as CEBAF… • Alignment specs • Quads positioned to +/-0.5mm in x & y, +/- 1.0mm in z • Vacuum specs • Beam line partial pressure of hydrogen <10-6 torr • Total average pressure of all other constituents less than 5x10-7 torr • Fabrication, welding, cleaning & handling, and leak checking specs still apply • 22631-S-001 Fabrication of Ultra-High Vacuum Equipment • 22632-S-001 Cleaning and Handling of U.H.V. Components • 22633-S-001 Welding Specification For U.H.V. Components • 22634-S-001 Helium Leak Test For U.H.V. Components • Note an update and modernization of our vacuum specs is underway

  5. Beam Transport Layouts – Spreaders & Recombiners • Two spreader regions • 1st and 2nd spreaders • Three recombiner regions • 1st , 2nd and transport recombiners

  6. Beam Transport Layouts – 1st Spreader Current Configuration 12GeV Configuration Changes… • Upgrade three QA quads to QRs and add H-steel to ten 1m dipoles • Relocate twelve quad girders, two YR septa magnets and six 1m dipoles • Elevation of the 2nd, 3rd, and 4th pass beams have changed between dipoles in the first step • Delete three 1m dipoles and one quad girder • Add two new curved dipoles, one 3m septa and the beamline to hall D Upgrade Relocate Delete New

  7. Beam Transport Layouts – 1st Spreader 12GeV 1st Spreader Layout – Identified Interferences • Songsheet level girder and dipole geometry used in layouts • Detailed documentation of actual geometry is limited • Compared songsheet geometry to photographs of each girder • Will need to confirm geometry by measuring every girder in each spdr and recombiner

  8. Beam Transport Layouts – 1st Spreader 12GeV 1st Spreader Layout –Potential solutions… • Identified potential solutions to eliminate interferences • Some existing girders require modification to eliminate interference • Will work with CASA to try and minimize alteration of existing girders by moving elements

  9. Beam Transport Layouts – 1st Spreader 12GeV Layout with Existing Stands Support stand modification assumptions for cost estimate… • Replace 10 vertical stands, modify 2 • Reuse vertical stand ceiling and floor foundations • Relocate if necessary • Add 2 new pedestal style stands to support 3m septa • Replace all girder to support stand brackets in first step between dipoles Replace Modify No Change

  10. Beam Transport Layouts – 1st Recombiner Current Configuration 12GeV Configuration Changes… • Upgrade three QA quads to QRs and add H-steel to ten 1m dipoles • Relocate fourteen quad girders, one YR septa magnet and seven 1m dipoles • Elevation of the 2nd, 3rd, and 4th pass beams have changed between dipoles in the first step • Delete three 1m dipoles • Add two new curved dipoles, one 3m septa Upgrade Relocate Delete New

  11. Beam Transport Layouts – 2nd Spreader Current Configuration 12GeV Configuration Changes… • Upgrade one QA quad to QR and add H-steel to eight 1m dipoles • Relocate seven quad girders, and four 1m dipoles • Elevation of the 4th pass beam has changed between dipoles in the first step • Delete three 1m dipoles, two curved dipoles, and two septa magnets • Add two new curved dipoles, two 3m septa, one 1.5m dipole, one 2m dipole, and two quad girders Upgrade Relocate Delete New

  12. Beam Transport Layouts – 2nd Recombiner Current Configuration 12GeV Configuration Changes… • Upgrade three QA quads to QRs, add QB to QC girder, and add H-steel to eight 1m dipoles • Relocate fifteen quad girders, and four 1m dipoles • Elevation of the 4th pass beam has changed between dipoles in the first step • Delete one 1m dipole, two curved dipoles, and one YR septa • Add two new curved dipoles, one 1.5m dipole, one 2m dipole, two 3m septa and the arc 10 beamline Upgrade Relocate Delete New

  13. Beam Transport Layouts – Transport Recombiner Current Configuration 12GeV Configuration Changes… • Upgrade two QA quads to QRs and add H-steel to eight 1m dipoles • Remove 2nd quad from three dbl QC girders (install on three new 5th pass girders), relocate two YA septa magnets to the extraction region • Elevation of the 4th pass beam has changed between dipoles in the first step • Delete three 1m dipoles, two curved dipoles, two YR septas, and one quad girder • Add three new QC girders, two new curved dipoles, two 3m septas, one 1.5m dipole, and one 2m dipole Upgrade Relocate Delete New

  14. Beam Transport Layouts – Selected Images

  15. Beam Transport Layouts – Selected Images

  16. Beam Transport Layouts – Selected Images

  17. Safety Considerations • Personnel Training • Jlab & sub-contractor • Radiation • Designated areas for containment and radiation survey of material that will be removed from the tunnel • Material handling • Provide provisions for lifting • Electrical Hazards • Package and support electronics, power leads and terminal blocks to control electrical hazards

  18. Cost Estimates – Spreader & Recombiner WBS Rollup WBS Elements I have covered today

  19. Cost Estimates - Highlighted WBS Girders & Stands - Procurements

  20. Cost Estimates - Highlighted WBS Vacuum - Procurements

  21. Risk Assessment • Technical - Low • Girders & Supports – very similar designs exist and are already proven • Alignment - same as existing machine • Schedule • Procurement - Low • No long-lead items identified • Installation – Low • Cost – Low • Good cost estimates for machined parts • Vendor & Jlab shop budgetary estimates

  22. Summary • Preliminary spreader/recombiner beam transport layouts, cost and installation estimates to support CEBAF at 12GeV are complete based on present scope • We are in a good position to support our DOE External Project Reviews this summer • We will continue to work closely with our friends throughout the lab (safety, CASA, installation, vacuum, alignment, RadCon, I&C, magnet measurement, operations, procurement & facilities) as we move forward • Detailed design will be completed to support assembly and installation schedules • We look forward to comments & recommendations from the committee

More Related