Update on LS1 Activities W.Baldini, N. Bondar, O.Maev,B. Schmidt LS1 Muon Meeting May-15th 2014
Ongoing Activities • LS1 activities: • activities ongoing on C-side M2-5: • Connectivity test slowly resuming, many problems with instabilities of virtual machines/CCPCs etc… it will take some more time • Problem with TELL1 (mutellc01) fixed (Oleg, Francesco); this week we would like to take more PDM data • Grounding improvement:almost done (3 more chambers…). Since last Wednesday it’s not possible to work due to HERSCHEL cable installation (~1 week). • Ferrite filters installation on M5 front done Our setup… HERSCHEL cabling
Ongoing Activities • HV: • Conditioning of C side: an M4R4 chamber (11C) found with a gap in short, replaced with a chamber recovered by Dmiitri (PNB094) • HV Connectors on A side (RDB-racks end) are being improved (Nikolai) before connecting them back • Check mapping and re-connect to CMBs Several connectors to be improved
Ongoing Activities • Next commissioning week June 23-27, we will try to turn on PNPI-HV-Chambers on A-side, so far we left the chambers unplugged. • For more details you can refer to the e-log: http://lblogbook.cern.ch/MUON/