CMS Area Working Group Meeting

CMS Area Working Group Meeting. Installation schedule for coming months. CEMESTE / 105 : May 2 nd 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains +Z area installation YB0 installation schedule Impact on start of central beam pipe installation

catori
Download Presentation

CMS Area Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMS Area Working Group Meeting martin.gastal@cern.ch

  2. Installation schedule for coming months CEMESTE/105: May 2nd 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains +Z area installation YB0 installation schedule Impact on start of central beam pipe installation -Z area installation USC55 Electronics installation in Control area LV system installation on top of By-pass Magnet/Cryogenics area installation TX54 martin.gastal@cern.ch

  3. Key milestones • Nov2006 Dec2006 Feb2007 March2007 May2007 • Ready for crates with cooling in UXC55 X2 level • 12/12/2006 27/02/2007 06/03/2007 17/04/2007 31/05/2007 • Start pre-cabling of TK • 15/05/2007 • Ready to insert TK • 28/08/2007 • Ready to cool down magnet • 31/08/2007 • LV system ready to power YE+1 • 15/06/2007 Hardelec contract Driven by TK piping and cable trays Compatible with LHC deadline Vacuum system & cryogenics commissioned Crucial for CMS commissioning martin.gastal@cern.ch

  4. Cable chains installation schedule martin.gastal@cern.ch

  5. Connect Cables From Patch p To racks On towers Ready for fibres TS LEA Work Packages almost complete Few pipes missing (compressed air) TS EL WPs all complete martin.gastal@cern.ch

  6. Connect Cables From Patch p To racks On towers Very challenging task!! Planning/coordination effort on-going martin.gastal@cern.ch

  7. YE+1 Draft schedule • TS-LEA: Criotec contract • Behind schedule… Short notice holidays… • More crews have been requested as from 07/05 to try and catch up • Lack of execution drawings but lots of on site coordination martin.gastal@cern.ch

  8. YE+1: very challenging environment Pipe, cables and fibres have to be organised martin.gastal@cern.ch

  9. YE+1 Draft schedule • TS-LEA: Spie Cegelec contract • In charge of on-detector cabling for both turbines and LV • Work in YEs towers between patch panels and racks • No proper execution drawings but supports from TS-EL and S Lusin • Activity very much on the critical path martin.gastal@cern.ch

  10. UXC55: Racks installation martin.gastal@cern.ch

  11. UXC55: Racks installation – Near side • TS-EL: Install cables for turbines • Start 16/05 for 2 weeks • Hadrelec • Far side completed first, missing cable trays have to be installed martin.gastal@cern.ch

  12. UXC55: Racks installation – Near side • TS-EL: Install cables for LV power distribution • Start 01/06 for 4 weeks • INEO • Routing to be provided by S Bally (nothing available at TS-EL) martin.gastal@cern.ch

  13. YB0 project eighth iteration Optimised schedule version 5: Milestone summary: Keys date to keep in mind martin.gastal@cern.ch

  14. YB0 +Z side Cosmi Ahead of schedule martin.gastal@cern.ch

  15. YB0 +Z side Very aggressive Procurement and assembly of cable trays will drive the sequence Target date martin.gastal@cern.ch

  16. YB0 -Z side Slower than expected insertion rate Can only start once +Z complete martin.gastal@cern.ch

  17. -Z Area installation FIN 56 installed Few more days needed for final alignment Next activity: Install forward beam pipe martin.gastal@cern.ch Design by CMS Integration group, April 2005.

  18. USC55 : TX54 shielding martin.gastal@cern.ch

  19. USC55 : TX54 shielding • Delivery from Pakistan: 30/03 • All material need to be cleared from the area • Tremie to be opened on 07/05, implications for lowering in USC55? • Safety barriers at the outline of the shaft in S2 should be removed when no load is lowered. This will facilitate the flow of personnel • Need to fill the gap between the 2 rows of plates • More steel plates needed • Budget code? martin.gastal@cern.ch

  20. USC55 : Control Area – CMS Electronics S2 (-1) martin.gastal@cern.ch

  21.    UPS supported      DSS commissioning in S2: start 10-11/05 Impact on Global run scheduled for 25/05      martin.gastal@cern.ch

  22. USC55 : Control Area – CMS Electronics S1 (-2) martin.gastal@cern.ch

  23. Services interruption • CV: • Cooling water: • Ventilation: • EL: • HV Power: • LV Power: • CSE: • Smoke detection: off in service area • HM: • TAIM cranes: • SDX5 crane: • UXC55 crane: AT-ECR works on transfer line during W16 • DSS: • Tests: S1 S2 start 21-22/05 • IT: • Network: • WiFi: martin.gastal@cern.ch

  24.    UPS supported Diesel Canalis DSS commissioning in S1: 21-22/05 Turbines cabinets: 2 installed 4 more to come New request from TK: accepted martin.gastal@cern.ch

  25. USC55 : CMS Electronics –Temporary Ctrl room Partition walls erected General services done Temporary access ctrl installed IT services installed Busy area already martin.gastal@cern.ch

  26. USC55 : Control Area – CMS Electronics S1 (-2) martin.gastal@cern.ch

  27.    UPS supported Diesel Canalis Turbines racks: 2nd to be installed this week New request from TK: accepted More requests are being considered martin.gastal@cern.ch

  28. Low-Voltage system USC55 – top of bypass martin.gastal@cern.ch

  29. USC55 –LV system installation Crucial for commissioning martin.gastal@cern.ch

  30. Installation of Magnet areaA project in itself! Sequence has been under intensive review Baseline available Actors from 3 departments (AT-PH-TS) martin.gastal@cern.ch

  31. Transfer line Cold Box DCCT CP1 & CP2 Discharge lines supports (design to be reviewed) 16 racks martin.gastal@cern.ch Cryo cabinets

  32. USC55- Magnet area • PH-CMI: Install support structure for transfer lines • No coactivity possible in the same area martin.gastal@cern.ch

  33. Areas where more scheduling effort is needed New items where scheduling effort is needed martin.gastal@cern.ch Design by CMS Integration group, April 2005.

  34. Very preliminary schedule Position against YB0 once scaffolding removed Lot more work needed martin.gastal@cern.ch

  35. Detailed studies on going….Dates are not relevant the focus is on the sequence • Areas where more work in needed to understand the sequence martin.gastal@cern.ch