CPM dengan Estimasi Waktu Tiga Aktivitas

CPM dengan Estimasi Waktu Tiga Aktivitas. Waktu-waktu Yang Diharapkan. Durasi = 54 Hari. C, 14. E, 11. H, 4. A, 7. D, 5. F, 7. I, 18. B 5.333. G, 11. Irwin/McGraw-Hill. The McGraw-Hill Companies, Inc., 1998. p(t < D). t. T E = 54. D=53.

clio-moreno
Download Presentation

CPM dengan Estimasi Waktu Tiga Aktivitas

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CPM dengan Estimasi Waktu Tiga Aktivitas

  2. Waktu-waktu Yang Diharapkan

  3. Durasi = 54 Hari C, 14 E, 11 H, 4 A, 7 D, 5 F, 7 I, 18 B 5.333 G, 11 Irwin/McGraw-Hill • The McGraw-Hill Companies, Inc., 1998

  4. p(t < D) t TE = 54 D=53 Bagaimana kemungkinan untuk menyelesaikan proyek ini dalam waktu kurang dari 53 hari?

  5. (jumlahkan variasi selama jalur kritis)

  6. p(t < D) t TE = 54 D=53 p(Z < -.156) = .5 - .0636 = .436, or 43.6 % (Appendix D) Ada kemungkinan 43.6% bahwa proyek ini akan diselesaikan dalam waktu kurang dari 53 minggu.

  7. Latihan • Bagaimana kemungkinan bahwa durasi proyek akan melebihi 56 minggu?

  8. p(t < D) t TE = 54 D=56 Penyelesaian Latihan p(Z < -.156) = .5 - .1217 = .378, or 37.8 %(Appendix D)