100 likes | 119 Views
LCLS SAFETY. Richard Hislop Construction Safety Coordinator. LCLS Safety Management. “LCLS Directorate ISEMS Plan” defines the roles and responsibilities of the Project Management Team (PMT) and holds the PMT responsible for the safe execution of the project.
E N D
LCLS SAFETY Richard Hislop Construction Safety Coordinator
LCLS Safety Management • “LCLS Directorate ISEMS Plan” defines the roles and responsibilities of the Project Management Team (PMT) and holds the PMT responsible for the safe execution of the project. • “LCLS ES&H Plan” defines the standards and requirements for safe construction. • All project work is to be based on the process of job hazards analysis and documented work authorizations. No work is so important on this project that it need be done without due consideration for safety.
Contracted work at Sector 20 and the Magnet Measurement Facility was completed 6/06. SLAC deconstruction of FFTB and assorted buildings was completed 8/27/06. Turner site work commenced 8/28/06. Tunneling operations will start 10/06. Construction Activities 46K contractor hours without injuries
FFTB SLAB REMOVAL Surprise Configuration FFTB Demolition Removal in Progress BrokenWindshield Value of PPE
PROJECT INJURY EXPERIENCE TO DATE Lost Time Injury Rate • SubContractors • 46 K Hours worked (08/28/2006) • Zero Injuries • LCLS Collaboration • 626 K Hours worked (08/28/2006) • Shoulder & back strain • 96 Days Worked Without Injuries (05/11/2006) Note: Injury rates based on 200 K hours (100 man years) of effort.
OUTREACH Management Safety Walks Lab-wide Communications
DOE Stanford Site Office Inspection Report LCLS Safe Performance Observations
WORK IN PROGRESS • Emergency / Crisis Management Coordination • Tunnel Rescue Training • Safe Performance Observations • Injector Safety Assessment Document • Fire Hazards Analysis