170 likes | 313 Views
Operations Update February 2001. Topics. Fall Mailing Season Christmas Holiday Rate Implementation. Standard A Volume Trends. 2000. 1998. 1999. 1997. Fall 2000 Standard A Volume Much Higher than Last Year. +1.5 Billion more pieces. Fall 2000 - Monitoring. DSAS Appointments
E N D
Topics • Fall Mailing Season • Christmas Holiday • Rate Implementation
Standard A Volume Trends 2000 1998 1999 1997
Fall 2000 Standard A Volume Much Higher than Last Year +1.5 Billion more pieces
Fall 2000 - Monitoring • DSAS Appointments • Operating Conditions • Communications • BSN’s, Account Managers, & Operations • HQ & Area Managers Operations
Observations of Mail Conditions By Inspection Service • Requested by the COO • Weekly Findings to AVP and MOS, • September through January 2001 • Corrective Actions to the COO • Focus on sites of Customer Concern
Fall 2000 Standard A Delays in Plants Similar to Last Year Fall Mailing
Flats Processing - AFSM 100 • Faster and Higher Throughput • OCR / BCR / Keying / Added Bins • Real Time Keying of Rejects • Focus on Incoming Secondary • Deploying Now • 165 operating as of January 2001 • additional 362 deployment begun
Fall 2000 • Election Mailings • AFSM 100 • Focused on Weekend Processing and Inventory levels • Communications • Operations, BSNs & Customer Support Teams
Christmas Holidays Priority Mail Processing Centers • Emery operated through Christmas • Area Operations used contingency plans to offload heavy destinating volumes • 10 PMPCs converted to postal facilities on January 7th
Christmas Holiday Logistics Issues • Most severe weather in a decade • High commercial airlines flight cancellations • Significant daily mail backlogs at major air hubs • Highway transportation suffered delays and cancellations • +200 dedicated network aircraft flights were canceled due to weather in 13 days
Christmas Holiday • Christmas Eve and Christmas Day delivery of Express Mail and obvious gifts • Dedicated networks moved +92 million pounds in 13 days • Cancellation volumes reached all time high • 314 Million on Dec 18th • Two Peak Plant & Delivery Day • 4 Billion cards & letters during holiday season
Rate Implementation • New Rates implemented January 7th • Plant Verified Drop Shipments entered until January 20 • Significant increase in Standard A volumes at plants from Jan 5 - 20th
Standard A Delays in PlantsVery High following New Rate New Rates Implemented
Rate Implementation Actions to Correct • COO directly involved • HQ and Area Operations telecons • COO and Area VP telecons • Area Action Plans implemented • Delays dropped dramatically last week
Summary Fall - Volume Christmas - Weather Rates - Recovered