WCCUSD Bond Program Construction Update. Pinole Valley High School Interim Campus 08/12/2014. Pinole Valley High School Interim Campus Site Plan. General Contractor JUV, Inc. Architect of Record WLC Architects Construction Managers SGI Construction Management Eddie Law
E N D
WCCUSD Bond ProgramConstruction Update Pinole Valley High School Interim Campus 08/12/2014
General Contractor JUV, Inc. • Architect of Record WLC Architects • Construction Managers SGI Construction Management • Eddie Law • Marc Alojepan • Verna Van • Inspector of Record Mark Eriksen Pinole Valley High School Interim CampusProject Team
Contract Amount $5,530,000 • Notice of Award 03/19/14 • Notice to Proceed 04/07/14 • Duration 130 days • Completion Date 08/15/14 Pinole Valley High School Interim CampusProject Team
Concrete poured at all retaining walls and walkway (final pour on-going) • AC paving (paving at front entrance area now and ramps) • Installation of fencing and gates – on-going • Power to all portables, final yesterday • Data line pull, termination, testing and labeling on-going • Fire alarm testing today • Installation of picnic tables and benches – on-going • Fire and domestic line chlorination (today), flush and bacteriological test • Installation of signage today • Kitchen health inspection conditional operational permit – Effective 8/8/2014 • Administration move and set-up – on-going • Teacher return/un-pack and classroom set-up – on-going • Final clean and AC striping – on-going Pinole Valley High School Interim CampusProject Status