160 likes | 280 Views
BOND PROGRAM UPDATE Building Tomorrow Today. Long Beach Community College District The Long Beach Rotary. Flex Day, March 28, 2007. AGENDA. Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex – Bid #2 LAC Central Plant Structure
E N D
BOND PROGRAM UPDATEBuilding Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007
AGENDA • Completed Construction Projects • Current & Upcoming Construction Projects • South Quad Complex – Bid #2 • LAC Central Plant Structure • LAC Learning Resources Center – Interim • LAC Learning Resources Center - Structure • South Quad Complex Structure • PCC Central Plant & Utilities • PCC Learning Resources Center • PCC Industrial Tech Phase 1 • PCC Industrial Tech Phase 2 • What’s Next? • Q & A
COMPLETED CONSTRUCTION PROJECTS Various Projects • PCC CDC – 4/06 • District Facilities & Warehouse Complex – Opened 1/17/06 • Men’s Gym Boiler Replacement – 4/06 • PCC MM/NN Lighting Upgrade – 4/05 • LAC Athletic Field – 3/06 • South Quad Complex Bid Pkg. #1 – 12/05 • LAC/LRC Utilities–6/06 • LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded) • East Campus Demolition
CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex – Bid Package #2 • Construction 98.5% Complete • Relocation of Water Main and Reclaimed Water Lines • Coordinated with Central Plant • Relocates Major Utilities Out of Golf Mall • Clears Way for Structures
CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC Central Plant – Structure • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction • Awarded to Siemens on DBOM Contract • Construction Starts April; Contractor Mobilizing • Completion Anticipated Summer 2008
CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC/Learning Resources Center – Interim Facilities • Construction 50% Complete • Anticipate Completion June 2007 • Modular Buildings to be Installed Saturday 3/31/07 • Utility Installation Complete Under Previous Phase (Bid Pkg. #1) • Includes Retrofit of Building E Basement
CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC/Learning Resources Center – Structure • Re-Bid Opening 3/29/07 • First Bids Rejected Move Planning Underway • Utility Installation Complete Under Previous Phase (Bid Pkg. #1) • Anticipate Start in June 2007; Completion in December 2008
CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex Structure (Bid Pkg. #3) • Construction Begun; Approx. 35% Complete • Overlaps Central Plant Early Piping Due to Utility Conflicts • Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. • Shifts Campus Center South of Carson off Lew Davis
CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Central Plant & Utilities • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction; Approx. 98.5% Complete. • Allows Utility Installation while Structure is in Plan Check • Clears Way for Structure • Structure in Plan Check • DBOM Contract Awarded to Siemens; Anticipate NTP April (NOI Issued)
CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Learning Resources Center • Awarded to Soltek Pacific • Construction Start in April Pending State Authorization • Modern Facility with Computer Lab and Multimedia • Expanded Facility • Bridge to Bldg. EE • Art Deco Style
CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • DSA Reviewing Changes; Out to Bid; Start in July 2007 • Modern Facility Houses Machine Tools and Welding Depts. • New Campus “Bookend” • S.E. Interim Bungalow Construction In Close Out Phase to Clear Tech 1 Site
CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 2 • Replaces Existing Antiquated Structures • Construction Underway; Approx. 53% Complete • Modern Facility Houses Aviation and Automotive Depts. • Impacted by DF&WC • Completion in Summer 2007
WHAT’S NEXT? Secondary Projects LAC & PCC • Multi-Disciplinary Academic Buildings (AA, BB, DD, EE) • Awaiting State Approval to Start Design; Antic. August 2007 • Construction 2009 • Retrofits Most of Existing Occupants in More Efficient Facility • Classrooms and Offices • Labs Including Computer, Art, Foreign Language, English, and Science Labs • Absorbs Some Portable Occupants • Student Services Centers • LAC Planning Underway; Construction to Start at End of South Quad Complex • PCC Awaiting State Funding; Will Start Construction in 2009/2010 • Centralizes Student Support Services (Admissions, Financial Aid, Cashier, Counseling, Job Placement, etc.) • New Building M • Gym (Q & R) Projects • Building E & F
QUESTIONS & ANSWERS Prepared By: Bond Management Team March 28, 2007 BUILDING TOMORROWTODAY