WCCUSD Bond Program Construction Update. Ohlone Elementary School Phase 1 – West Campus 02/11/14. Ohlone Elementary School Phase1 West Campus. Original Completion Date: July 21, 2013 Projected Completion Date: June 1, 2014 Percent Complete: 90%
E N D
WCCUSD Bond ProgramConstruction Update Ohlone Elementary School Phase 1 – West Campus 02/11/14
Original Completion Date: July 21, 2013 • Projected Completion Date:June 1, 2014 • Percent Complete:90% • Planned Move-in Date: June 1 to August 1 • Approved C/O’s to date: $1,471,876 = 8.4% Ohlone Elementary SchoolPhase1 West CampusGeneral Information
Ohlone Elementary SchoolPhase1 West Campus South Planters
Ohlone Elementary SchoolPhase1 West Campus Typical Classroom
Ohlone Elementary SchoolPhase1 West Campus Typical Classroom
Ohlone Elementary SchoolPhase1 West Campus Typical Learning Wall
Ohlone Elementary SchoolPhase1 West Campus Main Entry
Bid Advertisement: March 4, 2014 • Open Bids: April 8, 2014 • Notice of Award : April 16, 2014 (ratification) • Notice to Proceed: April 28, 2014 Ohlone Elementary SchoolInterim Housing PlanBidding Schedule
Ohlone Elementary SchoolInterim Housing Plan Site Plan – Phase 2.1
Ohlone Elementary SchoolInterim Housing Plan Site Plan – Phase 2.1
Ohlone Elementary SchoolPhase 3 Landscape Plan
Ohlone Elementary SchoolPhase 3 Site Plan
Current Status: Drawing Revisions • Submit to DSA: March 2014 • Back Check: July 2014 • Bid Advertise: July 23, 2014 • Open Bids: August 26, 2014 • Notice of Award: September 10, 2014 • Notice to Proceed: September 25, 2014 Ohlone Elementary SchoolPhase 3General Information