TRD Chamber production issues Planning and Hd Status TRD Collaboration Meeting GSI Clemens Adler
9xL1C1 finished 2xL1C1 being wired 3xL1C0 3xL2C0 1xL1C0 not usable? (Badly glued Padplane: maybe repair possible) Manpower: 2 technicians (Chamber building) 1 student (pad plane QA, chamber production) 3 Technicians (Front- L-profiles production) 1Technician from Bukarest (L-profiles production) Production rate: ~1Chamber/week (if no problems apear) Heidelberg Status TRD Collaboration Meeting GSI Clemens Adler
Layer 6 scenario: (decision this weekend) finish L6C0 material and include in next Dubna transport (in 3 weeks): ->1st Supermodule Chambers: May 1st (+transport from Dubna/Bukarest) decision in 3 weeks: additional transport to Dubna, ->1st Supermodule Ch: July 1st (+transport time) Layer 0 scenario: (decision this weekend) L0C0,L0C1 Material at Hd: May,1 L0C0 material in Dubna: June 15th ->1st Supermodule Chambers: July 1st (+transport) (better have a transport in Sept./Okt.?) (Assuming no Quality Problems) Schedule TRD Collaboration Meeting GSI Clemens Adler
Dubna: Chamber Transport Dates Supermodule assembly August: Supermodule assembly November: or built 1 L0C0 chamber at Hd TRD Collaboration Meeting GSI Clemens Adler
Bukarest Schedule • No further transport needed this year from point of view of Supermodule assembly. TRD Collaboration Meeting GSI Clemens Adler
Current distribution of types: Dubna: L1-6C0 Bukarest:L2C1, L3C1 GSI: L5C1, L6C1 HD: L1C1(part), L4C1 Ffm: L1C1 (rest), +? L1C1: produced in Hd until May, in Frankfurt starting July,1st- Oct ? Proposed change: Dubna: L0-5C0 Bukarest: L2C1, L3C1 GSI: L4C1, L5C1 HD: L1C1(part), L0C1 Ffm: L1C1(rest), +? L0 Implications for other Sites TRD Collaboration Meeting GSI Clemens Adler
Estimated SM production dates(just from Chamber point of view) • Transport delays not taken into acount • - Assumption: Money for 100% detector material is available Spring 2006 • All estimates based on 1 Chamber/week average production rate • Suggestion to use as a ‚base plan‘ until different production rates are observed TRD Collaboration Meeting GSI Clemens Adler
Cashflow? • In current plan: • Frankfurt is finished with 50% L1C1 in October 2005 • Heidelberg is finished with 50% L0C1 in February 2006 • GSI,Bukarest finish L2C1,L3C1,L4C1,L5C1 June 2006 Consequence: Frankurt/Heidelberg have to produce L2C1/L3C/L4C1/L5C1 TRD Collaboration Meeting GSI Clemens Adler
Hd: 7 L1C0 6 L2C0 24 L1C1 28 L0C1 Dubna: 12 L0C0 7 L1C0 6 L2C0 10 L3C0 8 L4C0 12 L5C0 Bukarest: 2 L1C0 2 L2C0 20 L2C1 20 L3C1 GSI: 20 L4C1 24 L5C1 Fankfurt: 20 L1C1 Chambers until End of 2005 TRD Collaboration Meeting GSI Clemens Adler