TRD (Pre-)Production Status

TRD (Pre-)Production Status. New Results/Experiences Problematic issues Production Plans Timescale. Voltage Divider Change. Was: 5.85 MOhm -> field cage current =360 uA Double resistance: 11.7 MOhm -> field cage current = 180 uA Compares to 0.5 uA Ion back drift current

wyman
Download Presentation

TRD (Pre-)Production Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRD (Pre-)Production Status • New Results/Experiences • Problematic issues • Production Plans • Timescale TRD status meeting GSI Clemens Adler

  2. Voltage Divider Change • Was: 5.85 MOhm -> field cage current =360 uA • Double resistance: 11.7 MOhm -> field cage current = 180 uA Compares to 0.5 uA Ion back drift current Savings in Power Supplies? TRD status meeting GSI Clemens Adler

  3. Leak Tightness of Prototype • Leak rate (determined for PRR): 1,5mbar*l/h • Gas sniffer shows leak in Padplane: ->some contact hole not glued • No other significant leaks found TRD status meeting GSI Clemens Adler

  4. Winding Frame New Winding Frame Design tested: • seems very stable • little contact area-> wire slips easily Probably design change necessary... TRD status meeting GSI Clemens Adler

  5. Soldering • Hotbar reflow soldering machine is ordered • Soldering will be done at IKF Frankfurt • Soldering on bare copper seems feasible • Tests at Panacol planned • Problem: need >10 micron tin to solder: -Padplane: silkscreen solderpaste then reflow in oven -Cable: apply tin by dipping TRD status meeting GSI Clemens Adler

  6. Soldering cont. More open questions: -Positioning of Cables: Aluminum template which gives Cable position-> fix with Tesa -Storage of Padplanes (IKF or Hd)? -Table for Soldering machine: build by IKF TRD status meeting GSI Clemens Adler

  7. Padplane Test Setup Measurement for shorts/contact by capacitance measurement. Principle works, but too much noise. Needed: Hardware TRD status meeting GSI Clemens Adler

  8. Production Plans • Material for chamber frame arrives next week • Start production of chamber frames+radiators • Start wiring as soon as ledges/ windingframe/ wire ready. • Store frames with wires until padplane panel ready • Start bonding as soon as padplanes are available • Final assembly when Fischer panel is available TRD status meeting GSI Clemens Adler

  9. Timescale TRD status meeting GSI Clemens Adler