1 / 16

TRD Electronics Flight Production

TRD Electronics Flight Production. Wim de Boer , Kai Gassmann, Florian Hauler, Andreas Sabellek , Mike Schmanau IEKP - Universität Karlsruhe (TH). Outline. TRD Electronics Overview Status of FM/FS TRD Electronics production at CSIST Results of Board-level acceptance testing Dec 06

tamah
Download Presentation

TRD Electronics Flight Production

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRD ElectronicsFlight Production Wim de Boer, Kai Gassmann, Florian Hauler, Andreas Sabellek, Mike Schmanau IEKP - Universität Karlsruhe (TH)

  2. Outline • TRD Electronics Overview • Status of FM/FS TRD Electronics production at CSIST • Results of Board-level acceptance testing Dec 06 • Report on replacement procedure of Actel FPGAs • Updated Time Schedule for FM U-Crates assembly and testing TIM Jan07, JSC

  3. TRD(U)-Electronics Overview V2 V2 UPSFE = TRD power supply for front end UDR = TRD data reduction board JINF = data concentrator and link to higher DAQ UHVG = TRD high voltage generator UFE = TRD front end UTE = TRD tube end UHVD = TRD high voltage distributor U = Uebergangsstrahlung UCrate = TRD electronics crate UBP = TRD backplane UPD = TRD power distribution box TIM Jan07, JSC

  4. QM2 UPD and U-Crate • One set of fully qualified QM2 TRD Electronics Crates (two set of FM Crates needed for complete TRD readout) Slow control connection to U-Crate Power supply connectors for U-Crate and 28V 6 UHVG JINF 3 UPSFE 6 UDR2 TIM Jan07, JSC

  5. Status of FM/FS Production at CSIST, Taiwan • DCDC Converter (S9056,S9048,S9053): FM/FS board production and test completed (May.06, presented on TIM Jul.06) • S9011AU Controller: FM/FS board production and acceptance test completed (Dec.06) • UBP: FM/FS production finished; Board assembly ongoing • UDR2: FM/FS board production and acceptance test completed (Sep/Dec.06, presented on TIM Oct.06) • UPSFE: FM/FS board production and acceptance test completed for 7/9 boards (Dec.06) • UHVG: reworked by VK; FM/FS production in progress, PCA delayed by components found out of specification (MIT) • JINF: FM/FS production ongoing (MIT) U Power Distribution (UPD): U DAQ Electronics (U-Crate): TIM Jan07, JSC

  6. S9011AU Controller FM/FS Test • Number of Boards tested: 4 (2 needed as FM) • Testprocedure (before/after Coating and ESS): • - Functional test via Lecroy communication • Signal and status lines tested with a DCDC converter (“needle” backplane used – no soldering on FM-boards necessary) • SSF test • Actel FPGAs with new Firmware are used • Some resistors mounted wrongly (unsoldered according to latest BOM) • 95001F: Short between two status lines on Actel pinout corrected (seen in functional test) Summary of Test Results: TIM Jan07, JSC

  7. UDR2 DAQ Board FM/FS Test • Number of Boards tested: 15 (12 needed as FM) • Testprocedure (before/after Coating and ESS in Dec.06): • - Functional test via AMSWire communication • Data acquisition with FM-Front-Ends • Current monitoring on Test-backplane • SSF test • No problems or errors seen Test-backplane Dec.06 TIM Jan07, JSC

  8. UPSFE FM/FS Test • Number of Boards tested: 9 (6 needed as FM) • Testprocedure (before/after Coating and ESS): • - Functional test via Lecroy communication • Linear Regulator test (28 circuits/board) on a Fusetest-backplane • Signal and status lines tested • Current monitoring • SSF test • Actel replacement after Firmware modification done, but mounted pairwise into wrong position (see Report on replacement procedure) • Some resistors with wrong values exchanged • 95003F: FPGA off-signal failure; Actel problem in off-state, will be exchanged • 95005F: one LR SSF failed after ESS; part failure found, will be exchanged UPSFE board 14x2 LR test circuits Fusetest Backplane Off-signal LEDs Status Jumpers Summary of Test Results: TIM Jan07, JSC

  9. Actel Replacement Procedure 1/2 Vacuum lifter • Solution to misplaced Actel FPGAs proposed and done by CSIST: desolder and swap same ICs to correct position • Thermal stress during desolder process is lower than in reflow soldering process of regular mounting Hot air nozzle Careful inspection necessary! Bottom fan 100°C FPGA pads have experienced 5 unavoidable de-/solder processes now TIM Jan07, JSC

  10. Actel Replacement Procedure 2/2 Manual soldering Iron@650°F + 5sec slide/edge Flux TIM Jan07, JSC

  11. FM UPD Assembly Status • CSIST technicians will follow UPD Assembly document prepared by Mike Schmanau • Production of needed I-Frames for UPD boards was finished with priority in Dec 06 • Cabling and soldering work on UPD boards is waiting for materials and tooling; most needed parts will arrive mid January Assembly discussion at CSIST TIM Jan07, JSC

  12. FM U-Crate Assembly Status • JINF production and testing has to be finished • UHVG production and testing has to be finished; PCA now waiting for new part supply • CSIST accepted to produce three set of flight cables for us - materials will be delivered mid January - U Cabling document is being prepared (lenghts and procedure) - final cable lengths already partly verified on wooden mockup (Andrey) TIM Jan07, JSC

  13. Time Schedule (updated) • Delays: shipment of UPD assembly materials and tools to CSIST; late Chinese New Year holidays in February • Full TRD readout test with FM Electronics will be performed in Aachen TIM Jan07, JSC

  14. Status Summary • Board-level acceptance tests were completed for needed FM boards in December06 (excluding Uhvg and Jinf); two UPSFE boards still need part exchange • Assembly of two FM set of UPD and U-Crate will start as soon as materials arrive at CSIST TIM Jan07, JSC

  15. Backup Slides TIM Jan07, JSC

  16. Actel off-signal Failure • Consequence: two UHVG boards cannot be switched to ON state • Lucky incident: after a replacement also observed on QM2 board with a new Actel Actel0 (on) output: high/low opens/closes transistor UHVG input: Small current (which is OFF state) Actel1(off) output: constant drop 0.6 V TIM Jan07, JSC

More Related