380 likes | 537 Views
NEPOOL Participants Committee Meeting April 4, 2003 Boston, MA. Stephen G. Whitley Senior Vice President & COO. Agenda. System Operations Gas Study Initiative SMD Market Operations Update Summer 2003 – “A Look Ahead” ISO/NEPOOL Cost Causation Update Demand Response Kickoff Update
E N D
NEPOOL Participants Committee Meeting April 4, 2003 Boston, MA Stephen G. Whitley Senior Vice President & COO
Agenda • System Operations • Gas Study Initiative • SMD Market Operations Update • Summer 2003 – “A Look Ahead” • ISO/NEPOOL Cost Causation Update • Demand Response Kickoff Update • Back – Up Details • Demand Response • New Generation • SW CT/Boston
Operation’s Highlights • Boston & Hartford Weather Pattern: • Temperatures were below the average (longest sustained 6-month period in 50 years) with normal to above normal precipitation. • Peak Load • Peak load of 18,039 MW at 20:00 hours on March 31. • During March • Minimum Generation on March 22 & 28. • Requested Shared Activation of Reserves (SAR) – March 5, 7 and 20(2); Provided SAR on March 29. • Resources postured on March 22, 23, 28 and 30. • Emergency Sales on March 3. • Solar Magnetic Disturbances – K7 forecasts on March 17 & 18. • The following were not implemented in March: • M/S#2; • M/S#3; • OP#4; and, • Class 6 Load Management.
Gas Study Update • Northeast very dependent on gas storage during winter heating season. • Too much cold weather beginning in November – January 2003 – Almost a peak design/month. • Depletion of working gas storage inventories. • Maintenance of line pack is a daily issue. • LNG is OK (Distrigas). • ISO-NE is performing a post-winter assessment to determine the capacity impacts on gas-fired generation.
Gas Study Update Winter Capacity of Gas Capable Units Includes 2003 units: AES GRANITE RIDGE, MILFORD PDC, SITHE FORE RIVER, SITHE MYSTIC
Gas Study Update Temperature Impacts on Gas-FiredGenerating Capacity, 12/02 – 3/03 Peak Day Temp.
Gas Study Update – Scope of Work “A Natural Gas Assessment & Reliability Implications for New England’s Electric Generation Sector”
Gas Study Update – Scope of Work, cont. “ A Natural Gas Assessment & Reliability Implications for New England’s Electric Generation Sector”
Gas Study Update – Scope of Work, cont. “A Natural Gas Assessment & Reliability Implications for New England’s Electric Generation Sector”
SMD Experience in March • Standard Market Design (SMD) cut-over was virtually seamless. • The March implementation date was designed to allow for a learning curve prior to the summer. • Energy prices were consistent with the cost of fuel: • Higher fuel costs in the first few weeks created higher energy prices; and, • Recently, energy prices have decreased consistent with the downward trend of fuel prices. • Software and business systems have generally worked well and functioning as designed. • Limited number of hardware and software issues, resulted in interruption of data flow.
SMD Experience in March (cont.) • Potential for error is elevated during this learning process: • Internally • Data – issues such as Non-PTF Loss Factors • Operator Error – RT dispatch or selection in day ahead • Externally • Methods used to reflect “Seller Choice” strategies • Self Scheduling • Internal decisions reviewed and business process and software tools enhanced to mitigate potential for repeat. • No reliability issues since going live. • NERC Control Performance within criteria. • Conditions experienced in Real-time so far: • Congestion; • Excess ramping curtailments; • Minimum generation emergency; • Major generation contingencies; and, • Emergency sales.
Day-ahead & Real-time Prices, ISO-NE Hub
Day Ahead – LMP Average by Zone & Hub (-1.4) (+0.1) (-1.3) (-2.7) (-2.8)
Real Time – LMP Average by Zone & Hub (-1.5) (+0.1) (-2.6) (-2.0) (-5.7) (+0.1) 97.4%
Summer 2003 Capacity AssessmentLeast Operable Capacity Margin - Weeks beginning June 7, 14 and 21 MW Projected Peak (50/50) 25,120 Operating Reserve Required 1,700 Total Operable Cap. Required 26,820 Projected Capacity 31,920 Assumed Outages 3,600 Total Capacity 28,320 Operable Capacity Margin 1,500
Summer 2003 Capacity AssessmentLeast Operable Capacity Margin - Weeks beginning June 7, 14 and 21 MW Projected Peak (90/10) 26,630 Operating Reserve Required 1,700 Total Operable Cap. Required 28,330 Projected Capacity 31,920 Assumed Outages 3,600 Total Capacity 28,320 Operable Capacity Margin (10)
Transmission Cost Allocation Workshops • ISO-NE presented “staff recommendation” for transmission cost allocation at the fourth and final stakeholder workshop on March 14. • Workshop participants included regulators from all six New England states and the FERC. (ISO-NE Board members also in attendance). • ISO-NE invited further comment beyond the workshop. • Next steps: • Present ISO-NE staff proposal to NECPUC and NEPOOL Tariff Committee (April); • Investigate least-cost-planning and resource parity issues with NECPUC and NEPOOL (April-June); • Present proposal to NPC and ISO-NE Board (May); and, • File proposal with the FERC (May).
ISO-NE Cost Allocation Method Proposal • ISO-NE/NEPOOL define upgrade categories. • Through RTEP, ISO staff recommends to SPARC/BOD each upgrade’s assignment to the appropriate category. • If the assignment can be reasonably made to both local or regional, Regional Cost Allocation is utilized. • Regional Mechanism – Project is “Regionalized” for the life of the project if: • Project provides loop/network benefits… 2-way traffic; and, • Project is 115-kV and above. • Any discretionary costs are borne by the entity requiring the special design (e.g. entities requesting underground).
New England Demand Response Summit • Radisson Hotel • 75 Felton Street • Marlborough, MA • April 17, 2003 • 8:30 a.m. – 12:00 p.m.
Demand Response(as of March 31, 2003) * Represents former Type 2 Interruptible Loads
New Generation Update (Revised) • No new generating resources were added in March • Approximately 3,382 MW expected by June 2003 • Generation Projects as of March 14, 2003 No.MW In Construction 6 3,382 with 18.4 approval Not in Construction 5 1,783 with 18.4 Approval
RMR Contracts • NRG • NRG filed Cost-of-Service RMR Contracts on February 26. • Annual fixed cost of about $180 million, including $44 million for normal and deferred maintenance. • FERC issued an order on NRG’s emergency motion on March 25, putting the “Reliability Cost Tracker” in place effective February 27. • ISO-NE to serve as escrow agent for these funds. • PPL • PPL Requesting Cost of Service RMR Contracts for Wallingford Station – Four of Five Nominal 45MW Peaking Units. • Filed on January 16, 2003. FERC issued Deficiency Letter on February 28, 2003. • PPL responded on March 31 and stated they will file an 18.4 Application for temporary deactivation effective July 1, 2003.
RMR Contracts (cont.) • PG&E (PGET and USGen New England) • Considering filing an 18.4 Application for Salem Harbor 1-4 effective October 1, 2004. • Governor has stated that units must be in environmental compliance by that date or shut down. • PG&E was planning environmental upgrades for compliance by October 1, 2006. • October 1, 2004 date is under appeal before a DEP ALJ. • ISO in discussion with DOER and DTE, National Grid and NSTAR on NEMA reliability needs and possible transmission improvements.