An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IPHC-LBNL Phone Conference News and updated ladder testing

  2. Topics • Two power bus cable design and status • Power regulator testing cable design and status • Ladder testing results post IPHC visit (MS) • General project progress. • Discussion

  3. Two power bus cable design • Design and layout are complete. • Gerbers have been sent to Rui at CERN PBC shop. • LBNL PO has been placed. • Waiting on delivery date.

  4. Two power bus cable design (cont) Outer and Inner driver board design and layout complete. Outer driver board has been sent for fabrication (10 pieces) to CERN PCB shop.

  5. Power Regulator Test Cable • Power regulator cable test schematic is complete. • Power regulator cable layout is underway. • We will be producing these PCBs locally, not in the CERN PCB shop.

  6. PXL Project News • Preparation for DOE yearly review at BNL in July • Primarily a project progress review with significant technical content. • A set of documentation for the PXL detector CD-2/3 is available at http://rnc.lbl.gov/hft/hardware/docs/sensor_review/summary_v2.doc • Additional documentation for this review will be posted soon. • New Virtex-6 based RDO motherboards. • Design is complete and testing has finished • 3 PCB architecture, new connectors, cables, 9U VME physical format. • Full complement of 10 assembled boards have been ordered for the prototype run RDO. Expected delivery in 3 weeks. • Significant Progress in mechanical structures. • See pictures next slide

  7. Hardware progress

  8. Discussion Topics • Ladder testing results. • Implications of instability in thresholds and noise. • Any other suggested testing? • Are these effects understandable through the analysis of the sensor design? • Ultimate 2 submission schedule. • Monthly phone conferences – propose a schedule. (2nd Tuesday of every month?) Please check your recurring meetings)