LCLS Ultrafast Science Instruments (LUSI)

LCLS Ultrafast Science Instruments (LUSI). Project Procurement Plan. David Pindroh – LCLS Procurement Manager August 2008. LUSI Project Procurement Plan. Procurement Management Overview Procurement Staffing & Organization Procurement Strategy Pre-Award Planning and Process Control

Download Presentation

LCLS Ultrafast Science Instruments (LUSI)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Ultrafast Science Instruments(LUSI) Project Procurement Plan David Pindroh – LCLS Procurement Manager August 2008

  2. LUSI Project Procurement Plan • Procurement Management Overview • Procurement Staffing & Organization • Procurement Strategy • Pre-Award Planning and Process Control • Long Lead Time and Major Procurements • Post-Award Follow up and Control • Summary

  3. Procurement Staffing and Organization LUSI Procurement utilizes the established and dedicated LCLS Procurement cell in conjunction with LCLS. LUSI based entirely on established SLAC & LCLS project procurement procedures . All Procurement staff participate in weekly LCLS/LUSI procurement status meeting with project management, headed by David Pindroh, LCLS Procurement. LCLS/LUSI Procurement incorporates the LCLS /SLAC Advanced Procurement Plan standards and reports.

  4. Purchasing Organization • LUSI Procurement Team includes: • Dedicated Procurement Management • Dedicated Procurement Support • Utilization of existing LCLS Procurement Cell Staffing • Integrated and collaborative support with: • LCLS Directorate • LCLS Project Office support • LUSI Project Management support • Central Procurement support & Back-up • DOE Site Office support • SLAC Operations and Business Services Support

  5. LCLS/LUSI Procurement Staffing levels • LCLS Purchasing Manager – David Pindroh (Dual reporting to BSD and Project Office) • Sr. Construction Contracts Administrator. (Carol Silva) • Construction Contracts Administrator (John Azevedo) • Sr. Buyer (III) – Equipment/Services (Beverly Freeman) • Buyer (II) – Fabrication/Equipment/On-site Services (John Escudero) • Buyer (I) – Low dollar Procurements (Sally Zapata) • Central Procurement – Back-up assistance as required. • Buyer II – John Gamble – Fabrications • Contract Administrator (MOU’s, Collaboration Agreements) - Pamela Elliot • Additional procurement assistance as needed.

  6. Procurement Workload • LCLS New Procurements • LUSI New Procurements

  7. Procurement Strategy • Utilization and Integration of LUSI into LCLS Advanced Procurement Planning Procurement (APP) tracking system. • All procurements over $100k and key Critical Procurements • Strategic Procurement Plans developed through APP • Advanced Procurement Planning (APP) includes determination of procurement methods and all required SLAC and DOE approval requirements • Weekly updated APP status reports with Project Management to track procurement process activities. • Posted APP status reports on SharePoint to provide weekly updates to Project Office, Project Management, SLAC Operations, BSD, and DOE site office. • Provides for continuous and proactive communication with all Project &Technical Staff, Vendors and Subcontractors.

  8. Pre-award Planning & process control • APP tracks and schedules critical reviews, approvals and procurement process critical dates. • Requisition & Specification/SOW procurement due dates • All Equipment Acquisitions tracked and scheduled to Correspond with the Project Installation Schedule. • Incorporates established Lead times • Provides for close coordination during specification preparation to identify key functional requirements, acquisition strategy, contract type and method of procurement. • Utilization of Full and Open Competition with Qualified Sources to the maximum extent possible • Incorporates DOE- SLAC Contract Review Board threshold approvals and process times • Internal Contract Review Board (CRB) review of all award packages > $100K • CRB and DOE RFP bid package review >$1M • Advance DOE Notice for sole source procurements > $100K • Advance notice of DOE approval on Buy American Act waivers > $100K • Procurements > $500K (Current Procurement System Approval)

  9. Sample APP Report

  10. Long Lead & Major Procurements • Long Lead Procurements • XPP Diffractometer/Detector Mover Components - $730K • CXI KB Mirror Systems (1.0 Micron) - $970K • Currently in RFI stage to assist with RFP acquisition strategy. • Other Major Procurements • CXI 0.1 Micron Mirror System ($970K) • XCS Diffractometer System ($460K ) • XCS Detector Mover ($224K ) • Large Offset Monochromator ( $1500K)

  11. Post award follow-up & Control • Critical Procurement Tracking reports provided during weekly meeting with Project Management team provides status for all identified critical procurements after award through receipt and final close out. • Reporting by responsible Buyer/Contract Administrator on order status, changes, updates to key project management. • Provides a forum to update management on potential issues. • Resolution of scheduling issues & expediting. • Provides strategy for problem resolution

  12. Sample Critical Procurement Report

  13. Summary • LUSI Acquisition Procurement Strategies established and tracked for equipment, installation and construction requirements. • LCLS Procurement staffing in place and established and fully integrated into the LUSI Project Team providing dedicated Procurement. • Request for Proposal (RFP) awards based on “Best Value” • RFI process already in place for Long Lead Time Major Equipment • Evaluation and basis of award criteria developed through close coordination and communication with project requestors.