THEMIS • PAYLOAD STATUS • Peter R. Harvey • Project Manager • University of California - Berkeley
Payload Status • PCA Assembly and Test
Payload Status Acoustics & Shock Vibration Spin Balance Thermal Vacuum FM2/FM3 Thermal Vacuum Storage
ASO/PAD Schedule 2 Note: RCS MEOP & Leak are performed after hours
ASO/PAD Manpower Manpower • 27 Max while at ASO • 31 Max while at PAD
Summary Summary Status • Probes and Probe Carrier are Flight Ready • Plans and Procedures for ASO/PAD in Good Shape • Shipment Contracted Two Trucks w/ Lead Car Ready Issues Potentially Impeding Launch Processing • None