An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of Hybrid Qualification and Tender • Final Technical Specifications • Hybrid types • Quality control, intermediate tests and inspections • Some results on FE-Hybrids w.r.t. these criteria • Visual inspections • Bonding • … • Delivery Profile of Pre-Production • Delivery Profile of Tender

  2. FE-Hybrids Types • Latest modifications in April 2003 • Lamination onto ceramic stiffener is a very critical operation • 12 different types of combinations (the opposite of what was originally intended!!) • TIB, TOB, TEC • 4 or 6 APV • Connector up and down • r and stereo ceramic (5) 1 TEC, 2 TOB, 2 TIB • APV25, positioning and bonding • Thermal cycle (simple, no bias) • Final acceptance test FHIT

  3. Quality Control • IPC-A-600F and IPC-A-610C, class 3 • Lamination: • detailed procedure, although recent failure is not understood. • Crucial visual inspection of lamination after all processing steps • Cleaning: has improved after some iterations • APV positioning and bonding is crucial (cost driving?) element • Certainly at limit of industrial standards • Detailed specs for precision placement and bonding • Dicing of APV-wafer is included as an option (1), ask for separated costing • Trace-ability of APVs at Wafer level • Trace-ability of individual APVs: Option (2) • Short temperature cycle is an option (3) • FHIT final functionality test (100%) and record for DB

  4. Positioning of APVs

  5. Positioning of APVs 95% should be in this area • TOB, Hybrid SA, 1st series, 55 measured • Kapton on ceramic • Overall shrink: 27 µm 0-1 0-4 0-5

  6. Positioning of APVs 95% should be in this area • TOB, Hybrid SA, 2nd series, 45 measured • Kapton on ceramic • Overall shrink: 31 µm 0-1 0-4 0-5

  7. Positioning of APVs 95% should be in this area • TIB, Hopp, series of 40 measured • Overall shrink FR4: 15 µm APV0-1 APV0-4 APV0-5

  8. Bonding Strength Hybrid_SA, TOB GS-Hopp, TIB

  9. Pre-Production I « M900 » • 300 TOB ordered (ceramic) • 16+80 delivered December 2002 • 78 -> CERN • 31 FNAL • 5 UCSB • 2 KA • 40 CERN • 29 with PA (25 bonded), 5 active thermal cycle • 100 delivered end Jan2003, • bad lamination • Can only be used for system tests • 20 TOB made in Feb/March, OK given end March • 80 to be done, in production • Lamination complete • 50 finished, 45 ok with FHIT, now in Strasbourg • 26 will be ready today • FHIT remained at factory • 200 TIB and 200 TEC ordered in Jan 2003 Problem not understood!

  10. Pre-Production II « Large volume order by CERN  » • 4370 TEC/TIB/TOB ordered, • 200+200+4370 considered as single production • With new designs never prototyped! • Qualification batch: 3 lots of ca. 100 in production • Lamination of TEC about to start after electrical test • Also bad circuits will be laminated for tests • Evaluation sample, delivery ca. May 6: • 10 TOB: 5x 4-APV_rphi_down, 5x 6-APV_rphi_up • 10 TIB: 5x 4-APV_rphi_down, 5x 6-APV_stereo_up • 10 TEC: 5x 6-APV_down, 5x 4-APV_up • 3x 90 TOB, TIB, TEC delivery (2 weeks) not before May 20 • Production batches • Start May 6(?), circuits tested mid June • Lamination starts June 20, 600-800 pcs/ week, finnish end July • Assembly and test: could start June 23, 600/week • Delivery to CERN starts July 7, finish beginning of Sept

  11. Tendering Status • Technical specifications are « frozen » • Documents for French administration: • Translation of Technical Specification into French • CCPT, Cahier des Clauses Techniques Particulières • CCAP, Cahier des Clauses AdministrativesParticulières • RDC, Règlement de la Consultation • Journal officiel des communautés européennes • All submitted on Monday, 07/04 to in2p3 • Official Start of Tendering 15th of April 2003 • All documents are/will be available on the ftp site: ftp://lepsi.in2p3.fr/pub/berst/CMS_HYBRIDS_AO /TIB; /TOB; /TEC; • “Appel d’offre ouvert” • Open for 52 days (end 17 June 17:00) • Opening of letters in week 25 (16/06) • Place Contract before 14th of July

  12. Production Delivery Profile