An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FP7-IA HFM JRA proposal • Outline • Motivation • General description • Proposed Work Packages FP7-IA HFM JRA proposal G. de Rijk (CERN)

  2. Future magnet needs 2 categories: max field <9 T : Nb-Ti technology Max field >9 T up to 15 T : Nb3Sn technology Common points: Radiation hardness, heat removal and temperature margin and The Low-beta quad, dispersion suppressor dipole and slim dipole need the Nb3Sn Jc at maximum coil fields >9 Tand in some cases >13 T FP7-IA HFM JRA proposal G. de Rijk (CERN)

  3. Work program To be seen in conjunction with the CERN program on HFMs • Support Studies • Study thermal properties • Study radiation resistance of components and coils • Model magnet • Design build and tests short dipole model (1 m - 1.5 m) • Prototype magnet • Design build and tests long prototype magnet (4 m - 8 m) Dipole or quadrupole: to be decided later depending on LHC needs FP7-IA HFM JRA proposal G. de Rijk (CERN)

  4. NED history and future requirements • FP6 NED project for a 1 m long, 12 T bore field, 88 mm aperture model • reduced version was approved (25% funded): preparation of the technologies needed for the model • Conductor development • Design studies (i.e. magnet design, thermal studies) • Component development (i.e insulators) • NED magnet was intended to upgrade the FRESCA facility to a 12T cable test station • The FRESCA facility upgrade is still strongly needed: key element for HFM conductor development and QA • Putting together the FRESCA needs and some common issues on the envisaged dipole needs: • Build a 1 m-1.5 m long, 13T bore field, 110 mm-130 mm aperture model magnet, to • Upgrade FRESCA • Constitute a test bed for the LHC and dipole magnets • Conductor: Profit from NED development and CERN HFM program FP7-IA HFM JRA proposal G. de Rijk (CERN)

  5. Prototype magnet • An important step towards an accelerator magnet is a full length prototype • For the LHC the choice is still open to what is the most relevant type: • 4 m - 8 m long, 200 T/m gradient, 130 mm aperture quadrupole or • 4 m - 8 m long, 13 T bore field, 130 mm aperture dipole • To test the scale-up of • Long conductor length of Nb3Sn cable • Coil manufacturing technology, winding, reacting (650C), handling of long coils • Support structure scale up FP7-IA HFM JRA proposal G. de Rijk (CERN)

  6. WP list FP7-IA HFM JRA proposal G. de Rijk (CERN)

  7. WP1 Management and Coordination • Task • Manage the package • Deliverables • Follow -up of the progress in the technical WPs • Regular reporting to EU and participants’ management (yearly report) • Planning • Financial follow up (quarterly report) • Budget: Material, travel 0.16 M€, Personnel 0.12 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)

  8. WP2 Support Studies • Tasks • Radiation resistance studies on materials for SC magnets • Nb3Sn • Insulation • Thermal stability studies • Heat deposition models • Heat removal models • Heat removal measurements • Deliverables and milestones start M1 • radiation resistance of Nb3Sn certified M36 • radiation resistent insulation certified M36 • rediation resistent impregnation certified M36 • Heat deposition and heat removal model M12 with experimental validation. • Thermal coil design parameters for M24 dipole and quad design • Budget: Material 0.8 M€ Personnel 1.7 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)

  9. WP3 High Field Dipole Model • 1 m-1.5 m long, 13 T, 110 mm-130 mm aperture dipole model magnet • Conductor selection and characterization • Coil geometry • Insulation type • Coil manufacturing technology • Mechanical support/pre-stress structure • Tasks • Conductor qualification • Make a design for the model • Tooling construction and installation • Produce the coils • Produce the cold mass • Test the model • Deliverables and milestones start M1 • Tooling installed 6M • Conductor qualified 8M • Design report 12M • Coils 18M • Cold mass 24M • Cold test 27M • Budget: Material 1.0 M€ Personnel 1.2 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)

  10. WP4 High Field prototype • 4 m - 8 m long, 130 mm aperture prototype magnet • 13 T Dipole or 200 T/m quadrupole, to be studied depending on LHC relevance • Coil manufacturing technology scale-up (shrinkage, expansion during reaction) • Mechanical support/pre-stress structure scale-up • Tasks • Make a design for the prototype • Tooling construction and installation • Produce the coils • Produce the cold mass • Test the model • Deliverables and milestonesstart M18 • Tooling M30 • Design report 30M • Coils 39M • Cold mass 45M • Cold test 48M • Budget: Material 1.9 M€ Personnel 1.1 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)

  11. Planning FP7-IA HFM JRA proposal G. de Rijk (CERN)

  12. Partners • Partners have been contacted recently with a request to form a collaboration • CEA-Saclay • Already expressed interest before, waiting for official answer • STFC-RAL • Already expressed interest before, waiting for official answer • CIEMAT • waiting for answer • Univ. Twente • Positive answer, details to be worked out • Univ. Wroclaw • waiting for answer • INFN Milano • waiting for answer • INFN Genova • Declined • Univ. Genève • Discussion ongoing • We will ask for more partners e.g. : • Univ. Berlin • KFA Karlsruhe FP7-IA HFM JRA proposal G. de Rijk (CERN)

  13. WP opt1 Very High Field Dipole Insert • 1 m long, 25 mm aperture HTS dipole insert to approach 20 T • B = 5 T-7 T in a 12 T-13 T background field • Bi-2212 round wire (Rutherford cable ) or YBCO 2nd generation tape • Technology demonstrator of possibilities to use HTS conductor in an accelerator magnet environment • To regain Europe’s place on this technology • Tasks • Conductor qualification • Make a design for the insert • Produce the coils • Assemble the insert • Test the insert • Planning M18 - M48 • Budget: Material 1.0 M€ Personnel 1.0 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)

  14. WP opt2 Two-in-one high field dipole model • 1 m long, 12 T bore field, 60 mm aperture two-in-one dipole model • Intended to show the way for the LHC dispersion suppressor upgrade • Tasks • Conductor qualification • Make a design for the model • Produce the coils • Produce the cold mass • Test the model • Planning M18 - M48 • Budget: Material 0.7 M€ Personnel 0.9 M€ FP7-IA HFM JRA proposal G. de Rijk (CERN)