CONTEXT AANBESTEDINGEN BETUWEROUTE EN HSL-ZUID. Ir. L.C. BOUTER 25 oktober 2005. TIJDSBALK KARAKTERISTIEK OMGEVING ONTVLECHTING NEDERLANDSE SPOORWEGEN ONTWERP BENADERING CONTRACTERING HSL-ZUID CONTRACTEN HSL-ZUID CONTRACTERING BETUWEROUTE KALENDER CONTRACTERING FINANCIËN
E N D
CONTEXT AANBESTEDINGENBETUWEROUTEEN HSL-ZUID Ir. L.C. BOUTER 25 oktober 2005
TIJDSBALK KARAKTERISTIEK OMGEVING ONTVLECHTING NEDERLANDSE SPOORWEGEN ONTWERP BENADERING CONTRACTERING HSL-ZUID CONTRACTEN HSL-ZUID CONTRACTERING BETUWEROUTE KALENDER CONTRACTERING FINANCIËN BUDGET ONTWIKKELING
- HSL-ZUID BESLUITVORMING: 70’er jaren TB 1998 BOUWPERIODE: 2000 april 2007 - BETUWEROUTE BESLUITVORMING: 80’er jaren TB 1996 BOUWPERIODE: 1998 dec. 2006 TIJDSBALK
HSL-ZUID - VERVOERSPROJECT - INZET OP PRIVATISERING BETUWEROUTE - INFRA PROJECT - TRADITIONELE AANPAK KARAKTERISTIEK
- BETUWEROUTE EN HSL-ZUID - TALRIJKE VERGUNNINGEN - VELE BESTUURSORGANEN - VEEL DOSSIERS GRONDVERWERVING - WELSTANDSCOMMISSIES BETUWEROUTE - TIJDENS BOUW VOORTGEZETTE DISCUSSIES OVER “NUT EN NOODZAAK” OMGEVING
TOT 1995 INFRASTRUCTUUR EN VERVOER EXLUSIEF BIJ NS NA 1995 - INFRASTRUCTUUR BIJ NS RAILINFRABEHEER (NS-RIB) - VERVOER BIJ NS REIZIGERS (NIET MEER EXCLUSIEF) 2003 UITPLAATSING NS-RIB (PRORAIL) UIT NS HOLDING NAAR HET RIJK (MINISTERIE V&W) ONTVLECHTING NEDERLANDSE SPOORWEGEN
HSL-ZUID SPOORLIJN IN DOORGAANDE “GEÏNTEGREERDE” BAK MET MOOI PROFIEL BETUWEROUTE VANUIT TRADITIONELE SPOORBOUW ONTWERP BENADERING
- ZWAAR STEMPEL PRIVATISERING EMBRYONAAL IDEE: ÉÉN CONTRACT MET VERVOERDER GEKOZEN VOOR D&C VOOR DE ONDERBOUW DBFM VOOR DE BOVENBOUW CONCESSIE VOOR HET VERVOER - NAAST AANLEG OOK ONDERHOUD EN VERVOERSDIENSTEN GECONTRACTEERD CONTRACTERING HSL-ZUID
ONDERHANDELING CONTRACTEN ONDERBOUW prijs aanbieding risico’s opdrachtgever CONTRACT INFRASPEED VOLGENS ANGELSAKSICHS MODEL NAAR NEDERLANDS RECHT (SIC!) CONTRACTEN HSL-ZUID
TRADITIONELE BENADERING ALLEEN AANLEG DEELS NIEUWE CONTRACTEN (E&C; ALLIANTIE) “STAP VOOR STAP” WERKEND VANUIT ONDERBOUW NAAR BOVENBOUW DE ZIN VAN EEN DBFM-CONTRACT VOOR BOVENBOUW ONDERZOCHT LOPENDE DE UITVOERING V/D ONDERBOUW (DBFM DBM D&C E&C RAW) CONTRACTERING BETUWEROUTE
HSL-ZUID - GECONCENTREERD IN PERIODE VANAF 1998 TOT BEGIN 2001 - GEPLANDE OPLEVERING IN APRIL 2007 HARD BETUWEROUTE - VANAF 1996 “STAP VOOR STAP” TOT IN 2004 - GEPLANDE OPLEVERING IN DECEMBER 2006 (AANVANKE-LIJK IN JULI 2005) KALENDER CONTRACTERING
SPANNING: GERESERVEERD BUDGET VS WERKELIJKE KOSTEN BUDGET IN RIJKSBEGROTING TEN TIJDE VAN TB OP BASIS VAN 50% VERWACHTINGSWAARDE 20% ONZEKERHEIDSMARGE IVM TEGENVALLERS EN RISICO’S IN DE UITVOERING NIET GEBUDGETTEERD FINANCIËN
BUDGET ONTWIKKELING IN DE BELEIDSFASE VEEL GROTER DAN IN DE UITVOERINGSFASE (WIJZIGING SCOPE PROJECTOPDRACHT) SCOPE WIJZIGINGEN TIJDENS DE UITVOERING ZIJN RELATIEF DUUR BOVENDIEN: OVERGROTE DEEL BUDGETSTIJGING IS HET GEVOLG VAN SCOPE WIJZIGINGEN FORS DEEL KOSTENSTIJGING IS GEVOLG VAN INFLATIE (INDEX) - KOSTENSTIJGING DOOR TEGENVALLERS EN RISICO’S IN DE UITVOERING BLEVEN BINNEN 20% ONZEKERHEIDSMARGE BUDGET ONTWIKKELING