MT Continuum Status Gerry Cullison, SSP Mark Campbell, MT Continuum Team Mike Coyle, AIM team 23 April 2013
Overview • MT Continuum overview • Application to other communities • Project status • Lessons learned for other NETC communities
MT Continuum Project Strategic Systems Programs (SSP) re-engineering 30+ week training pipeline for TRIDENT Ballistic Submarine (SSBN) Missile Techs (MTs) into blended just-enough/just-in-time ILE-conformant Instructor Led (ILT) and Interactive Multimedia Instruction(IMI) segments AIM CPM and LO Module toolsets part of SSP’s baseline business process for this re-engineering First major end-to-end design, development, and maintenance project that’s defining CPM/LO Module business rules and data exchange mechanisms
MT Continuum Project MT Continuum team: SSP - Requirements Owners, Afloat Delivery System Contractor team – ILT development, IMI Storyboard development, SMEs NAWCTSD / AIM team - CPM/LO Module support NUWC – LMS/CCS (Seaware) LSI, Inc. - ISD and IMI design/development Chenega Logistics – CM/QA agent for SSP SLC (NETC CCA for MT curriculum) Fleet – SMEs
Application to Other Communities Based on NETC-mandated JDTA as fleet performance requirement basis for learning content design and development (NAVEDTRA 137) Closely coordinated with NAVEDTRA 136 development Hands-on production phase development of complete LO Module ILT lessons/sections and design of IMI lessons/sections as well as definition of new JDTA/LO Module versioning concepts Integrated development and maintenance environment for blended, SCORM NAVEDTRA 136-compliant learning content Bi-directional interface between LO Module and GFI CBT toolset for integrated ILT/IMI development/maintenance
Project Status • Plan, Analyze & Design Phases Completed • Delivery Method Analysis Process still needed • Scientific/Justifiable/Repeatable • Development fully underway. Development effort is at the halfway point. • Assessment, Performance Testing (NAVEDTRA 132) • Large emphases on Implementation, Evaluation and Maintenance. • Versioning, LMS interface.
Lessons learned for other NETC communities • JDTA • Foundation. Getting this right cannot be overemphasized. • Maturity of Design Documents and Processes • IMDP, Learning Objectives (ISD Considerations), Process Documents, Assessment Design, Time to Train Estimations, Delivery Method Analysis