MT Continuum Status Jake Aplanalp, AIM Pgm Mgr Mike Lueken, LM SS for SSP Wendy Pester, CSF for SSP Joe Farbo, LSI Jamie Stewart, AIM team 23 Aug 11
Overview • MT Continuum overview • Application to other communities • Project status • Lessons learned for other NETC communities
MT Continuum Project Strategic Systems Programs (SSP) re-engineering 30+ week training pipeline for TRIDENT Ballistic Submarine (SSBN) Missile Techs (MTs) into blended just-enough/just-in-time ILE-conformant Instructor Led (ILT) and self-paced segments AIM CPM and LO Module toolsets part of SSP’s baseline business process for this re-engineering First major end-to-end design, development, and maintenance project that’s defining CPM/LO Module business rules and data exchange mechanisms MT Continuum team: SSP - Requirements Owners Contractor team – ILT dvlp, self-paced input, SMEs NAWCTSD / AIM team - CPM/LO Module support LSI, Inc. - ISD and self-paced content design/development CFS – CM/QA agent for SSP
Application to Other Communities • Based on NETC-mandated JDTA as fleet performance requirement basis for learning content design and development • Closely coordinated with NAVEDTRA 136 development • Hands-on production phase development of complete LO Module ILT lessons/sections and design of self-paced lessons/sections • Integrated development and maintenance environment for blended, SCORM and 136-compliant learning content • Bi-directional interface between LO Module and LSI Venus.net CBT toolset for self-paced development/maint.
Project Status • Plan, Analyze and Design Completed • JDTA • Establishment of initial 3 major projects • Revised 9-project structure • Approval of learning objectives • Ongoing development of ISD considerations elements as part of script-storyboard effort • Development (production) Phase underway 15 May 11 • 9 projects exported from CPM to LO Module for production development in AIM I Rel 5.0 on fedsun • SWS AIM I instance to transition to NETPDTC hosting by 1 Oct 11
Lessons Learned for Other NETC Communities • Completion of supporting documentation in Design Phase is crucial – (IMDP, ASDD, process documents) • Establish standard for estimating TTT in Design Phase • Establish change request process in Design Phase • Complete Development IMS/POA&M in Design Phase – better activity duration estimates for process steps.
Issues/Concerns • “End to end” surveillance/maintenance test on TLO/ELO in process to: • confirm existing change impact identification functionality in CPM and LO Module • identify near-term updates • refine longer-term enhancements • Testing begun by Mark Campbell and Mike Lueken (LMMS) w/ favorable results • Identified critical issues addressed as part of AIM I Rel 5.0 • Further testing surveillance testing on LDC is still required and ongoing with Rel 5.0 by Jamie Swaim (CSF) • Team continues to refine versioning business rules/process
Modernized AIM Modernized AIM can tie the entire process together