MT Continuum Status. Jake Aplanalp, AIM Pgm Mgr Gerry Cullison, SSP Mark Campbell, LM SS for SSP Mike French, LSI. 4-6 May 2010. Overview. MT Continuum overview AIM toolset role Issues and concerns Process flow. MT Continuum Prototype Project.
E N D
MT Continuum Status Jake Aplanalp, AIM Pgm Mgr Gerry Cullison, SSP Mark Campbell, LM SS for SSP Mike French, LSI 4-6 May 2010
Overview • MT Continuum overview • AIM toolset role • Issues and concerns • Process flow
MT Continuum Prototype Project Strategic Systems Programs (SSP) re-engineering 30+ week training pipeline for TRIDENT Ballistic Submarine (SSBN) Missile Techs (MTs) into blended just-enough/just-in-time ILE-conformant Instructor Led (ILT) and self-paced segments AIM CPM and LO Module toolsets part of SSP’s baseline business process for this re-engineering First major end-to-end design, development, and maintenance project that’s defining CPM/LO Module business rules and data exchange mechanisms MT Continuum team: SSP / contractors - Requirements Owners NAWCTSD / AIM team - CPM/LO Module support LSI, Inc. - ISD and self-paced content design/development
AIM Tool Usage • Dedicated MT Continuum Prototype CPM and AIM I Rel 4.0 instances hosted in Orlando • Local AIM I Rel 4.0 instances running at GD-AIS Pittsfield (SMEs) and at LSI Jax (ISD/CD) • Significant progress made to date on bi-directional data exchange between LO Module and LSI Venus.net LDC authoring toolset • Excellent feedback from MT Continuum team on enhanced functionality and performance needed in CPM & LO Module
AIM Tool Usage(contd) • Status: • Per GD-AIS feedback, performance-enhanced version of AIM I Rel 4.0 running locally in Pittsfield and Jax as well as on Orlando server • Per GD-AIS feedback, significant enhancements made to AIM I Rel 4.0 storyboard functions/output • Several additional enhancements recommended by GD-AIS being analyzed by AIM team for incorporation into AIM I Rel 5.0 (Jul 10 delivery) • AIM team continues troubleshooting performance and reliability issues with Orlando AIM I Rel 4.0 instance
Issues/Concerns • “End to end” surveillance/maintenance test on TLO/ELO occurred to: • confirm existing change impact identification functionality in CPM and LO Module • identify near-term updates • refine longer-term enhancements • Test conducted by Mark Campbell and Mike Lueken w/ favorable results & identified critical issues to be addressed before full-rate production
Modernized AIM Modernized AIM can tie the entire process together
Application to Other Communities • Based on NETC-mandated JDTA as fleet performance requirement basis for learning content design and development • Closely coordinated with NAVEDTRA 136 development (Mark Campbell & Jamie Stewart involved in project) • Potential “Poster Child” for ongoing NETC Continuum effort with all Centers • Integrated development and maintenance environment for blended, SCORM and 136-compliant learning content
FRM Inputs on Enhancements • To be covered this afternoon during AIM/CPM Demo