Parts and Requirements for Preliminary Design Review by Jorg Fischer, University of California - Berkeley

This overview provides a quick overview of the parts and materials required for the Preliminary Design Review, including specific requirements and quantities. It also covers information on data bases, lists, and long-lead items.

prices
Download Presentation

Parts and Requirements for Preliminary Design Review by Jorg Fischer, University of California - Berkeley

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Parts Requirements • Preliminary Design Review • Jorg Fischer • University of California - Berkeley

  2. Overview • Parts & Materials Overview • Requirements • Parts Quantities Quick Overview • Parts List • Data Bases, Lists • Parts, Long-Lead Items

  3. Requirements • GSFC 311-INST-001 • Instructions for EEE Parts Selection, Screening, Qualification • Minimum EEE Parts Criteria for Level 3 = Moderate level of risk, as permitted by cost constrains • Parts in compliance with 311-INST-001, Level 3 (Grade 3) requirements and Standard parts • Use of GSFC PPL 21 (GSFC Preferred Parts List), design permitting • Particle Impact Noise Detection (PIND), per MIL-STD-750 and MIL-STD883, required for cavity devises • Impose on manufacture, if possible • When needed, have DESC approved test facility perform testing • Customer Source Inspection (CSI) and/or Destructive Physical Analysis (DPA) for complex or known problem devices

  4. Requirements • (continued) • Non-standard EEE parts will require at a minimum: • Plastic Encapsulated Microcircuits (PEM) Selection, Screening, and Qualification (NASA/TP-2003-212244, PEM-INST-001) • DPA, Preconditioning, Highly Accelerated Stress Test (HAST), and CSAM (Center for Surface Analysis of Materials) Testing • Radiation Testing • Total Ionizing Dose (TID) Requirement is 66Krads (si) • - Review existing test data from GSFC, JPL, and manufacturer • - Review NASA “where used” historical data • Parts can be used, if data and or orbit requirements equal or exceed • THEMIS requirements • Cobalt 60, TID testing will be performed as needed • Single Event Effects (SEE) use existing data or historical use (similarity) • - Whenever possible designers will use latchup immune devices

  5. Parts & Material Quantities • Quick Overview SCM, EFI, BMD, BEB, DFB, FGE/PCB, DCB/ETC, LVPS, SST, ESA, Backplane: • 5 Flight + 1 Flight Spare • EFI • Preamps: • 6 Flight per SC+ 4 Flight Spares (40 Total) • Spin Plane Boom (SPB): • 4 Flight per SC+ 4 Flight Spares (28 Total) • Axial Boom (AXB): • 2 Flight + 2 Flight Spares (14 Total)

  6. EEE Parts List - I • UCB/SSL QA will maintain an EEE Parts • Identification List (PIL) • The PIL will contain: • Manufacturer’s generic part number • Military Part Number or SCD number • Manufacturer(s) • Where used (unique assembly) / Quantity • Quantity used • Quantity ordered • Lot/Date Code • Radiation Status (TID/SEL) • Alert Status • Comments

  7. EEE Parts List – II • (continued) • Parts will be procured to an approved Parts List. • Schedule permitting, will procure common buy. • Procurement of devices will be based upon design engineer’s confidence-of-use factor of 70%. • Unique, high-dollar items will be based on a 90%-100% confidence level. • Minimum Attrition / Spares factor of 20%-30% will be applied to flight procurement quantities. Non-standard devices will have more spares. • Schedule and cost permitting, engineering test units (ETU) will use flight qualified parts, especially, where minimum buy quantities are imposed. • ETU and Flight unit • Procurement will run concurrently

  8. EEE Parts List – III • (continued) • Flowdown Performance Assurance Implementation • Plan (PAIP) requirements on subcontractors • Parts Control Board (PCB) • PCB members are: Themis QA, Design Engineer, and Themis Project manager, or representative • PCB shall review EEE part for: • Testing, Screening, and Qualification Failures • Alerts (e.g., GIDEP) • Review Non-Standard Parts Requirements

  9. Data Bases & Lists • Material DB List is posted on Apollo

  10. Data Bases & Lists • Data Base on FTP Apollo: • MS Excel DB, THM_All_Parts_Rev20.xls

  11. Data Bases & Lists • Summary Parts Lists • Individual Board Parts Lists

  12. Long-Lead EEE Parts 1 Main List, 102 Active Parts, 11 TID,SEE Test Parts

  13. Long-Lead EEE Parts • (continued) • Amptek • A121, ESA, on order • A225F, SST, pending • A250F, ETC, pending • Honeywell • HX6228, SRAM, DFB, DCB, ETC, SST, on order • 3. 3D-Plus • PROMETHEE1, Preamp, SCM, on order • PROMETHEE2, V-regulator, SCM, on order • MMSD08256804S-C-1S, SRAM, DCB, on order