An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BOND PROGRAM UPDATEBuilding Tomorrow Today Long Beach Community College District Citizens’ Oversight Committee April 9, 2007

  2. AGENDA • Completed Construction Projects • Current & Upcoming Construction Projects • South Quad Complex – Bid #2 • LAC Central Plant Structure • LAC Learning Resources Center – Interim • LAC Learning Resources Center - Structure • South Quad Complex Structure • PCC Central Plant & Utilities • PCC Learning Resources Center • PCC Industrial Tech Phase 1 • PCC Industrial Tech Phase 2 • What’s Next? • Q & A

  3. COMPLETED CONSTRUCTION PROJECTS Various Projects • PCC CDC – 4/06 • District Facilities & Warehouse Complex – Opened 1/17/06 • Men’s Gym Boiler Replacement – 4/06 • PCC MM/NN Lighting Upgrade – 4/05 • LAC Athletic Field – 3/06 • South Quad Complex Bid Pkg. #1 – 12/05 • LAC/LRC Utilities–6/06 • LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded) • East Campus Demolition

  4. LAC Construction Phasing

  5. CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex – Bid Package #2 • Construction 98.5% Complete • Relocation of Water Main and Reclaimed Water Lines • Coordinated with Central Plant • Relocates Major Utilities Out of Golf Mall • Clears Way for Structures

  6. CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC Central Plant – Structure • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction • Awarded to Siemens on DBOM Contract • Construction Starts April; Contractor Mobilizing • Completion Anticipated Summer 2008

  7. CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC/Learning Resources Center – Interim Facilities • Construction 50% Complete • Anticipate Completion June 2007 • Modular Buildings to be Installed Saturday 3/31/07 • Utility Installation Complete Under Previous Phase (Bid Pkg. #1) • Includes Retrofit of Building E Basement

  8. CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC/Learning Resources Center – Structure • Re-Bid Opening 3/29/07 • First Bids Rejected Move Planning Underway • Utility Installation Complete Under Previous Phase (Bid Pkg. #1) • Anticipate Start in June 2007; Completion in December 2008

  9. CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex Structure (Bid Pkg. #3) • Construction Begun; Approx. 35% Complete • Overlaps Central Plant Early Piping Due to Utility Conflicts • Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. • Shifts Campus Center South of Carson off Lew Davis

  10. PCC Construction Phasing

  11. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Central Plant & Utilities • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction; Approx. 98.5% Complete. • Allows Utility Installation while Structure is in Plan Check • Clears Way for Structure • Structure in Plan Check • DBOM Contract Awarded to Siemens; Anticipate NTP April (NOI Issued)

  12. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Learning Resources Center • Awarded to Soltek Pacific • Construction Start in April Pending State Authorization • Modern Facility with Computer Lab and Multimedia • Expanded Facility • Bridge to Bldg. EE • Art Deco Style

  13. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • DSA Reviewing Changes; Out to Bid; Start in July 2007 • Modern Facility Houses Machine Tools and Welding Depts. • New Campus “Bookend” • S.E. Interim Bungalow Construction In Close Out Phase to Clear Tech 1 Site

  14. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 2 • Replaces Existing Antiquated Structures • Construction Underway; Approx. 53% Complete • Modern Facility Houses Aviation and Automotive Depts. • Impacted by DF&WC • Completion in Summer 2007

  15. WHAT’S NEXT? Secondary Projects LAC & PCC • Multi-Disciplinary Academic Buildings (AA, BB, DD, EE) • Awaiting State Approval to Start Design; Antic. August 2007 • Construction 2009 • Retrofits Most of Existing Occupants in More Efficient Facility • Classrooms and Offices • Labs Including Computer, Art, Foreign Language, English, and Science Labs • Absorbs Some Portable Occupants • Student Services Centers • LAC Planning Underway; Construction to Start at End of South Quad Complex • PCC Awaiting State Funding; Will Start Construction in 2009/2010 • Centralizes Student Support Services (Admissions, Financial Aid, Cashier, Counseling, Job Placement, etc.) • New Building M • Gym (Q & R) Projects • Building E & F

  16. QUESTIONS & ANSWERS Prepared By: Bond Management Team – Cordoba Corporation April 9, 2007 BUILDING TOMORROWTODAY