Update on FCPS Construction/Renovation Projects. August 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 Contract Sum: $9,061,000 Change Orders to Date (1): $2,878.14
E N D
Update on FCPS Construction/Renovation Projects August 2009
Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date (1): $2,878.14 • Current Phase: 1 (On Schedule) • Estimated Completion: 19%
Cassidy Elementary – Renovation Rendering of Final Façade
Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • Storm sewers installed on south side and across new front parking lot. • Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed. • Grading started at sidewalks and playground. Concrete retaining walls in place. • Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed. • Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete. • Foundations for stage complete. • Music Classroom addition foundation, 1st floor slab, 2nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going. • Plumbing rough-ins have continued as masonry walls are installed. • Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed.
Cassidy Elementary – Renovation • Current Work Effort (August): • Storm sewers will continue as site work allows. • New 3” domestic water main service will complete. • Site grading will complete around the playground. Sidewalk/paving work will complete at playground area. • Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated. • Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place. • HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area. • Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area. • Electric conduit and rough-ins to continue.
Cassidy Elementary – Renovation New Admin. Addition 2nd Fl. New Playground Retaining Walls Interior Gym New Stage & Music Room Addition
Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date (2): $12,098.51 • Current Phase: 1 (On Schedule) • Estimated Completion: 30%
Russell Cave Elementary – Renovation Rendering of Final Façade
Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Exterior walls at new addition are complete, block and brick. Interior walls are complete. • Roof trusses and metal deck at new addition have been installed. • Interior of Kitchen/Cafeteria is complete. • Renovation of (4) classrooms on the south side continues. • Masonry restoration on the exterior of the original building in process. • New electric service for new addition to be complete before school begins. • Current Work Effort (August): • Interior ramp and stair in new addition will be poured. • Masonry restoration of the east wall will be completed. • Roof at new addition will be installed. • Install new ductwork in new addition and four classrooms. • Install overhead electrical rough-in and temporary power and lights in new addition and four classrooms. • Construction fence will be reinstalled around new addition before the start of school.
Russell Cave Elementary – Renovation New Addition New Addition Interior of Cafeteria New Serving Line in Kitchen
Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: 8%
Arlington Elementary – Renovation Rendering of Final Façade
Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Selective demolition in existing building. • Earthwork and Site utilities are ongoing. • Building foundations are in place at the gym, kitchen and cafeteria. • Relocation of utilities and installation of manhole in Arceme are in progress. • Under slab utilities at custodial receiving and Mechanical room are in place. • Masonry and hollow metal door frames started on west wall of the gymnasium. • Current Work Effort (August): • Demolition of existing masonry at building to remain and construction of replacement wall. • Site storm sewer installation. • Underground utilities will continue. • Masonry wall construction at the addition continues. • 95% complete with demolition in existing building. • Continue utility rough-in at the existing building. • Installation of temporary roof at the existing building.
Arlington Elementary – Renovation Demolition Work Earthwork & Site Utilities Foundation Work Under Slab Utilities
Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date (1): $8,667 • Current Phase: 1A (On Schedule) • Estimated Completion: 29%
Bryan Station Middle – Renovation Rendering of Final Façade
Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • Cafeteria prepared for student use. Finishes and HVAC completed in this area. • Corridors barricaded from construction areas and safe egress signs put in place. • New sanitary sewer lines nearly complete. • New kitchen and kitchen dock work progressing. • Current Work Effort (August): • Installing new HVAC rooftop equipment. • Installing footers for new Music Suite addition at rear of building. • Concentrate on library renovation for turnover to owner as soon as possible. • Repair Wood gym floor.
Bryan Station Middle – Renovation Foundations for New Addition Earthwork Prep for New Addition Concrete Poured at New Dock Café Prior to New Floor
Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date (1): $2,732.40 • Current Phase: 1, 1a, 1b (On Schedule) • Estimated Completion: 16%
Leestown Middle – Renovation Rendering of Final Façade
Leestown Middle – Renovation • Work Completed in Last 30 Days: • Phase 1demolition efforts continue. • Structural shoring at Cafeteria and in Corridor. • Kitchen foundation wall and plumbing rough-in complete. • Existing utilities have been tied back in. • Interior masonry wall erection started. • Current Work Effort (August): • Demolition in Phases 1, 1a & 1b will continue. • Floor slab for the new Kitchen will be poured. • Electrical and Plumbing rough-ins on-going. • Masonry load bearing masonry at Kitchen to start. • Erection of new Fire Walls to begin. • Masonry restoration has begun. • Erection of structural steel to begin.
Leestown Middle – Renovation Kitchen Plumbing Rough In Demo for New Café Window Admin. Suite Demo Looking From Courtyard Demo Admin. Suite
Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Judy Construction Co. (proposed) • Substantial Completion Date: Fall 2010 (est.) • Contract Sum: $4,333,000 (pending Board approval) • Change Orders to Date: $0 • Current Phase: Phase 1
Lafayette High Stadium – Replacement Existing Campus
Lafayette High Stadium – Replacement Existing Football Stadium
Lafayette High Stadium – Replacement New Football Stadium
Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date (2): $10,044.51 • Current Phase: Construction • Estimated Completion: 51%
Central Bus Garage – Adaptive Reuse • Work Completed in Last 30 Days: • Exterior • Bollards installed • Light pole bases have been installed • Dumpster pad completed • Exterior plumbing completed • Generator gas line installed • Waste management systems in place • Fluid storage steel erected • Interior • Mezzanine in place and elevated slab poured • Underslab plumbing in place • Slab under mezzanine has been placed • Bus lifts poured in place • Excavation complete for trench drains
Central Bus Garage – Adaptive Reuse • Current Work Effort (August): • Parking lot to be completed • Wheel stops at the bus parking to be placed • Paint booth to be complete by the 21st • Interior MEP continues
Central Bus Garage – Adaptive Reuse New Fluid Storage Addition Bus Parking Equipment Installation