1 / 32

Update on FCPS Construction/Renovation Projects

Update on FCPS Construction/Renovation Projects. August 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 Contract Sum: $9,061,000 Change Orders to Date (1): $2,878.14

cormac
Download Presentation

Update on FCPS Construction/Renovation Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on FCPS Construction/Renovation Projects August 2009

  2. Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date (1): $2,878.14 • Current Phase: 1 (On Schedule) • Estimated Completion: 19%

  3. Cassidy Elementary – Renovation Rendering of Final Façade

  4. Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • Storm sewers installed on south side and across new front parking lot. • Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed. • Grading started at sidewalks and playground. Concrete retaining walls in place. • Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed. • Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete. • Foundations for stage complete. • Music Classroom addition foundation, 1st floor slab, 2nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going. • Plumbing rough-ins have continued as masonry walls are installed. • Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed.

  5. Cassidy Elementary – Renovation • Current Work Effort (August): • Storm sewers will continue as site work allows. • New 3” domestic water main service will complete. • Site grading will complete around the playground. Sidewalk/paving work will complete at playground area. • Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated. • Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place. • HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area. • Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area. • Electric conduit and rough-ins to continue.

  6. Cassidy Elementary – Renovation New Admin. Addition 2nd Fl. New Playground Retaining Walls Interior Gym New Stage & Music Room Addition

  7. Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date (2): $12,098.51 • Current Phase: 1 (On Schedule) • Estimated Completion: 30%

  8. Russell Cave Elementary – Renovation Rendering of Final Façade

  9. Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Exterior walls at new addition are complete, block and brick. Interior walls are complete. • Roof trusses and metal deck at new addition have been installed. • Interior of Kitchen/Cafeteria is complete. • Renovation of (4) classrooms on the south side continues. • Masonry restoration on the exterior of the original building in process. • New electric service for new addition to be complete before school begins. • Current Work Effort (August): • Interior ramp and stair in new addition will be poured. • Masonry restoration of the east wall will be completed. • Roof at new addition will be installed. • Install new ductwork in new addition and four classrooms. • Install overhead electrical rough-in and temporary power and lights in new addition and four classrooms. • Construction fence will be reinstalled around new addition before the start of school.

  10. Russell Cave Elementary – Renovation New Addition New Addition Interior of Cafeteria New Serving Line in Kitchen

  11. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: 8%

  12. Arlington Elementary – Renovation Rendering of Final Façade

  13. Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Selective demolition in existing building. • Earthwork and Site utilities are ongoing. • Building foundations are in place at the gym, kitchen and cafeteria. • Relocation of utilities and installation of manhole in Arceme are in progress. • Under slab utilities at custodial receiving and Mechanical room are in place. • Masonry and hollow metal door frames started on west wall of the gymnasium. • Current Work Effort (August): • Demolition of existing masonry at building to remain and construction of replacement wall. • Site storm sewer installation. • Underground utilities will continue. • Masonry wall construction at the addition continues. • 95% complete with demolition in existing building. • Continue utility rough-in at the existing building. • Installation of temporary roof at the existing building.

  14. Arlington Elementary – Renovation Demolition Work Earthwork & Site Utilities Foundation Work Under Slab Utilities

  15. Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date (1): $8,667 • Current Phase: 1A (On Schedule) • Estimated Completion: 29%

  16. Bryan Station Middle – Renovation Rendering of Final Façade

  17. Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • Cafeteria prepared for student use. Finishes and HVAC completed in this area. • Corridors barricaded from construction areas and safe egress signs put in place. • New sanitary sewer lines nearly complete. • New kitchen and kitchen dock work progressing. • Current Work Effort (August): • Installing new HVAC rooftop equipment. • Installing footers for new Music Suite addition at rear of building. • Concentrate on library renovation for turnover to owner as soon as possible. • Repair Wood gym floor.

  18. Bryan Station Middle – Renovation Foundations for New Addition Earthwork Prep for New Addition Concrete Poured at New Dock Café Prior to New Floor

  19. Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date (1): $2,732.40 • Current Phase: 1, 1a, 1b (On Schedule) • Estimated Completion: 16%

  20. Leestown Middle – Renovation Rendering of Final Façade

  21. Leestown Middle – Renovation • Work Completed in Last 30 Days: • Phase 1demolition efforts continue. • Structural shoring at Cafeteria and in Corridor. • Kitchen foundation wall and plumbing rough-in complete. • Existing utilities have been tied back in. • Interior masonry wall erection started. • Current Work Effort (August): • Demolition in Phases 1, 1a & 1b will continue. • Floor slab for the new Kitchen will be poured. • Electrical and Plumbing rough-ins on-going. • Masonry load bearing masonry at Kitchen to start. • Erection of new Fire Walls to begin. • Masonry restoration has begun. • Erection of structural steel to begin.

  22. Leestown Middle – Renovation Kitchen Plumbing Rough In Demo for New Café Window Admin. Suite Demo Looking From Courtyard Demo Admin. Suite

  23. Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Judy Construction Co. (proposed) • Substantial Completion Date: Fall 2010 (est.) • Contract Sum: $4,333,000 (pending Board approval) • Change Orders to Date: $0 • Current Phase: Phase 1

  24. Lafayette High Stadium – Replacement Existing Campus

  25. Lafayette High Stadium – Replacement Existing Football Stadium

  26. Lafayette High Stadium – Replacement New Football Stadium

  27. Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date (2): $10,044.51 • Current Phase: Construction • Estimated Completion: 51%

  28. Central Bus Garage – Adaptive Reuse Façade

  29. Central Bus Garage – Adaptive Reuse • Work Completed in Last 30 Days: • Exterior • Bollards installed • Light pole bases have been installed • Dumpster pad completed • Exterior plumbing completed • Generator gas line installed • Waste management systems in place • Fluid storage steel erected • Interior • Mezzanine in place and elevated slab poured • Underslab plumbing in place • Slab under mezzanine has been placed • Bus lifts poured in place • Excavation complete for trench drains

  30. Central Bus Garage – Adaptive Reuse • Current Work Effort (August): • Parking lot to be completed • Wheel stops at the bus parking to be placed • Paint booth to be complete by the 21st • Interior MEP continues

  31. Central Bus Garage – Adaptive Reuse New Fluid Storage Addition Bus Parking Equipment Installation

  32. Tonight’s Agenda Items

More Related