1 / 18

Bond Construction Update Citizens Oversight Committee

Bond Construction Update Citizens Oversight Committee. Long Beach Community College District April 18, 2011. EDUCATE  ENGAGE  EMPOWER . Agenda. Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court District Wide – Monument Signs

lotte
Download Presentation

Bond Construction Update Citizens Oversight Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER

  2. Agenda • Completed Construction Projects • LAC Parking Structure • LAC Building O Complex • PCC Walnut Ave. Arrival Court • District Wide – Monument Signs • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • LAC South Walkway Extension • LAC W Trailers Demo • LAC Master Landscape • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Tech1 (Sheet Metal) • Upcoming Construction Projects • PCC Building CC Retrofit • Q & A

  3. Completed Construction Projects LAC Parking Structure – Measure E 2008 • Spaces for 893 vehicles • Solar generation system is commissioned and operational • Project is complete and being used for student parking

  4. Completed Construction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Occupants for Building O2 are Foundation, ERD, LBNP and ALCI • IITS and BMT are moved in, Warehouse Facility moving • Project is complete with some punch walk items left

  5. Completed Construction Projects PCC Walnut Ave. Arrival Court - Measure E 2008 • UU/VV demo completed • Site converted to a parking lot April 4th, 2011

  6. Completed Construction Projects District Wide – Monument Signs Measure E 2008 • District Wide Monument Signs • Locations: • LAC-Clark/Conant – completed January 8, 2011 • PCC-20th/Walnut Ave. – Completed March 30, 2011 • Installation of building designators for LAC Bldg. O1 and O2 completed LAC Monument Sign LAC Bldg. Designator PCC Monument Sign

  7. Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • New home for A&R, Counseling, Health Services, Cashier, Transfer Center • Project currently in demolition and structure upgrade • Construction fence and temporary walkways complete • End of construction anticipated Summer 2012

  8. Current Construction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Total annual estimated savings of 1.5 mil. Kwh • Project started Fall 2009; currently hydro seeding all affected areas(All phases) • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Buildings C,D, G,H, & J are connected • Buildings B and E will be scheduled by end of April • Exterior lighting and controls upgrades • All parking lots north of Lew Davis are on new system • New Reclaimed Water tie-ins to irrigation connected • New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P • New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P • Anticipated end of construction Winter 2011

  9. Current Construction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • G2K Construction working on demolition and utilities • End of Construction anticipated Fall 2011

  10. Current Construction Projects LAC South Walkway Extension Measure E 2008 • 99% complete • Palm trees to be replaced May 2011 • Continues Master Plan pedestrian corridor

  11. Current Construction Projects LAC W Trailers Demo - Measure E 2008 • Green Giant Construction has removed old W trailers • Grading of lot to commence in this month • Project will address storm run off issues with bio swales • Site to be converted to a parking lot • Estimated project completion Summer 2011

  12. Current Construction Projects LAC Master Landscape - Measure E 2008 • Currently in Design Phase • Quad areas North and South areas of Bldg. A bid Winter 2012 • Remaining areas designed at 25% • Scope includes new hardscape/landscape and pedestrian pathways

  13. Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 • MDAB building remodel project • Phase 1 of 2 currently under construction • Project currently in demolition and structural reinforcement • Phase 1 Project to be completed Summer 2012

  14. Current Construction Projects PCC Tech 1 (Sheet Metal) - Measure E 2008 • Currently in bid process • Construction to start Summer 2011 • Projected to be completed before Fall 2011

  15. Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • Approved by DSA on 1/27/11. Currently in bid process • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012

  16. Liberal Arts Campus Site Plan l i b e r a l a r t s

  17. Pacific Coast Campus Site Plan p a c i f i c c o a s t

  18. QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER

More Related