Bond Construction Update Citizens Oversight Committee. Long Beach Community College District April 18, 2011. EDUCATE ENGAGE EMPOWER . Agenda. Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court District Wide – Monument Signs
E N D
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER
Agenda • Completed Construction Projects • LAC Parking Structure • LAC Building O Complex • PCC Walnut Ave. Arrival Court • District Wide – Monument Signs • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • LAC South Walkway Extension • LAC W Trailers Demo • LAC Master Landscape • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Tech1 (Sheet Metal) • Upcoming Construction Projects • PCC Building CC Retrofit • Q & A
Completed Construction Projects LAC Parking Structure – Measure E 2008 • Spaces for 893 vehicles • Solar generation system is commissioned and operational • Project is complete and being used for student parking
Completed Construction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Occupants for Building O2 are Foundation, ERD, LBNP and ALCI • IITS and BMT are moved in, Warehouse Facility moving • Project is complete with some punch walk items left
Completed Construction Projects PCC Walnut Ave. Arrival Court - Measure E 2008 • UU/VV demo completed • Site converted to a parking lot April 4th, 2011
Completed Construction Projects District Wide – Monument Signs Measure E 2008 • District Wide Monument Signs • Locations: • LAC-Clark/Conant – completed January 8, 2011 • PCC-20th/Walnut Ave. – Completed March 30, 2011 • Installation of building designators for LAC Bldg. O1 and O2 completed LAC Monument Sign LAC Bldg. Designator PCC Monument Sign
Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • New home for A&R, Counseling, Health Services, Cashier, Transfer Center • Project currently in demolition and structure upgrade • Construction fence and temporary walkways complete • End of construction anticipated Summer 2012
Current Construction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Total annual estimated savings of 1.5 mil. Kwh • Project started Fall 2009; currently hydro seeding all affected areas(All phases) • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Buildings C,D, G,H, & J are connected • Buildings B and E will be scheduled by end of April • Exterior lighting and controls upgrades • All parking lots north of Lew Davis are on new system • New Reclaimed Water tie-ins to irrigation connected • New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P • New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P • Anticipated end of construction Winter 2011
Current Construction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • G2K Construction working on demolition and utilities • End of Construction anticipated Fall 2011
Current Construction Projects LAC South Walkway Extension Measure E 2008 • 99% complete • Palm trees to be replaced May 2011 • Continues Master Plan pedestrian corridor
Current Construction Projects LAC W Trailers Demo - Measure E 2008 • Green Giant Construction has removed old W trailers • Grading of lot to commence in this month • Project will address storm run off issues with bio swales • Site to be converted to a parking lot • Estimated project completion Summer 2011
Current Construction Projects LAC Master Landscape - Measure E 2008 • Currently in Design Phase • Quad areas North and South areas of Bldg. A bid Winter 2012 • Remaining areas designed at 25% • Scope includes new hardscape/landscape and pedestrian pathways
Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 • MDAB building remodel project • Phase 1 of 2 currently under construction • Project currently in demolition and structural reinforcement • Phase 1 Project to be completed Summer 2012
Current Construction Projects PCC Tech 1 (Sheet Metal) - Measure E 2008 • Currently in bid process • Construction to start Summer 2011 • Projected to be completed before Fall 2011
Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • Approved by DSA on 1/27/11. Currently in bid process • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012
Liberal Arts Campus Site Plan l i b e r a l a r t s
Pacific Coast Campus Site Plan p a c i f i c c o a s t
QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER