February 4, 2013. All Experimenters’ Meeting. Shutdown 2012. Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning has begun TeV & Muon Rings – Partially available for tours with approval and appropriate training.
E N D
February 4, 2013 All Experimenters’ Meeting
Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning has begun TeV & Muon Rings – Partially available for tours with approval and appropriate training
Power Outages - Unplanned • Feeder 46B • Tuesday, January 29th • Isolated fault (Between F4 & P71) • Repairs pending manhole access • Feeder 36 • Wednesday, January 30th • Isolated fault • Believe it was a splice • Manhole access on Friday to investigate
Power Outages – MSS Bypass Project • NS7 Oil Switch • Monday, January 7th for ~ 2 weeks • 0800-1000 power off to connect the generator • Impacts – NS7 Service Building and Adjacent Enclosures (NM2, NM3) • PS1 Oil Switch (moved earlier than original) • January 28thfor ~ 2 weeks (In progress) • Will be running house power off a generator • Impacts – PS1 Service Buildings and Adjacent Enclosure (P01) & Target Service Building (TSB) • NS1 Oil Switch • February 11thfor ~ 2 weeks • Will be running house power off a generator, negotiating requirements • Impacts – NS1 Service Building and Adjacent Enclosures (N01, NM1) • MS1 & MS2 • March 11thfor ~ 2 weeks • Will be running house power off a generator • Impacts – MS1 & MS2 Service Buildings and Adjacent Enclosures (M01, M02, & M03)
Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html ANU - http://www-cons/ Proton Source -http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html