An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of EURISOL Yorick BLUMENFELD We acknowledge the financial support of the European Community under the FP6 “Research Infrastructure Action - Structuring the European Research Area” EURISOL DS Project Contract no. 515768 RIDS . The EC is not liable for any use that can be made of the information contained herein.

  2. THE EUROPEAN PLAN NuPECC recommends the construction of 2 ‘next generation’ RIB infrastructures in Europe, i.e. one ISOL and one in-flight facility. The in-flight machine would arise from a major upgrade of the current GSI facility: FAIR, while EURISOL would constitute the new ISOL facility The EURISOL Road Map • Vigorous scientific exploitation of current ISOL facilities : EXCYT, Louvain, REX/ISOLDE, SPIRAL • Construction of intermediate generation facilities: SPIRAL2, HIE-ISOLDE, SPES • Design and prototyping of the most specific and challenging parts of EURISOL in the framework of EURISOL_DS.

  3. The EURISOL_DS in the 6th framework • Detailed engineering oriented studies and technical prototyping work • 20 participants from 13 countries • 21 contributors from Europe, Asia and North America • Total Cost : 33 M€ • Contribution from EU : 9.16 M€ • Continues to July 2009 • 12 Tasks in 4 Topical Areas: • Targets • Accelerators • Physics, beams and Safety • Beta Beams

  4. User Requirements (Trento meeting; Jan 2006) • Internal report 10-25-2007-001 • Energy: Main LINAC up to 150A MeV for 132Sn; second LINAC up to 5A MeV and possibility for 0.1 to 0.7A MeV (astrophysics)+ low energy • Energy variability: 0.5% (below 20A MeV) and 1A MeV (above 20A MeV) • Energy definition : 0.1% • Time resolution : 0.5ns or better(?) • Time structure : 8.8 MHz (buncher-chopper) and retain also 88MHz • Beam sharing: 1 MMW target and 3 direct 100 kW targets of which 2 can be used simultaneously • Pure beams • Emittance : 2p mm.mrad and 2mm2 beam spot

  5. New baseline scheme with extended capabilities • 2 injection lines for H,D, He and A/q=2 ions • SARAF scheme up to 60 MeV/q • IPNO scheme from 60 to 140 MeV/q • CEA scheme from 140 to 1000 MeV/u • cw beam splitting at 1 GeV (1 line 4 MW + 3 lines 100 kW) • Total length of the linac: ~240 m 4 MW H- B stripper Elliptical 704 MHz 1 GeV/q RFQ 176 MHz HWR 176 MHz 3-SPOKE 352 MHz H-,D- 100 kW H+, 3He2+ =0.09 =0.15 =0.03 =0.047 =0.65 =0.78 H+,D+, 3He++ 1.5 MeV/u foil stripper 60 MeV/q 140 MeV/q >200 MeV/q D, A/q=2 10 36 31 63 97

  6. EURISOL parallel cw Proton extraction 1 GeV Multiple Extraction • 3 splitting stations • 4 simultaneous users for cw proton beams: • 1  4 MW • 3  0100 kW (continuously adjustable) • Unique ability of EURISOL at present

  7. New Target ConceptMMW target for fission fragments

  8. Double effusion line prototype(E. Bouquerel, L. Penescu) Bellows Cu body 2xwater cooled transfer lines 2x20cm containers RIB 2 pneumatic valves ISOLDE cold FEBIAD MK7Ion source Heat screen 1.4GeV protons

  9. Schematic lay-out Target-ion sources • Beam preparation lay-out: • Two complete beam preparation chains • Two parallel mass-purified beams for on-line experiments • Two charge breeders: • EBIS (fast, low capacity, low background, narrower charge state distribution, provides intensity also for light elements) • ECR (slow, high capacity, high background, access to intense beams including stable ones) • Modular (easy to expand) • Robust (electrostatic deflectors without moving parts) Pre-separators, beam gates Electrostatic deflection Ion cooling and bunching High-resolution separators Charge breeding: EBIS and ECR q/m selection Post-acceleration and Experimental areas

  10. Design of the post-accelerator SPIRAL-2 philosophy:Smoothest beam dynamics (regular FDO lattice, low number of -sections), Modular solution and simple cryostats, Separated vacuum (safety with FP), Warm focusing (easier for alignement), Possibility to insert diagnostics at each period, ease of tuning Main technical requirements: Only 2-gap cavities (high q/A acceptance) Max. accelerating fields 7.8 MV/m Nominal operation for A/Q between 4 and 8

  11. Fragmentation of 132Sn (Preliminary results) Fragmentation of 132Sn on Be D. Perez and D. Dragosavac

  12. Intensity (pps) Yields after acceleration Comparison between facilities a) Kr isotopes a) Yield for in-flight production of fission fragments at relativistic energy

  13. Radioactive ISOL beam yields 2020 2016 2012 present

  14. Possible Locations? The Site Investigation Panel (chaired by Alan Shotter) will investigate the implementation and cost of EURISOL in these 3 hypotheses

  15. Time scales 2005 2007 2009 2012 2020 FAIR Project definition Construction Exploitation

  16. Why a EURISOL User Group? • To build up an identifiable User Community for EURISOL • To continuously update the EURISOL Physics Case; while Task 10 will now mainly concentrate on instrumentation. • To continue to furnish input to the EURISOL concept after the end of the DS • To interact with the user communities of the current ISOL facilities.

  17. Goals of this week • Updating of the Physics Case • Putting EURISOL in perspective with the other worldwide initiatives. • Examining the current technical solutions in the light of the physics requirements (Thursday morning) • Discussing the practical organization and future actions of the UG in the framework of the future of EURISOL (Wednesday, 14:30-16:00)