1 / 9

Heidi Pacini Staff Engineer

Heidi Pacini Staff Engineer. Load/Gen Balance Spreadsheet Inputs November 10, 2011 SWG Resource Team Conference Call. List of Inputs. Subregional coincident peak demand 2022 generation by area and resource type Targeted planning reserve margin On-peak capacity value by resource type

teo
Download Presentation

Heidi Pacini Staff Engineer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Heidi PaciniStaff Engineer Load/Gen Balance Spreadsheet Inputs November 10, 2011 SWG Resource Team Conference Call

  2. List of Inputs • Subregional coincident peak demand • 2022 generation by area and resource type • Targeted planning reserve margin • On-peak capacity value by resource type • Firm transfers between sub-regions at time of peak

  3. Coincident Peak Demand • Source: 2022 Common Case load forecast

  4. 2022 Generation • Renewable Resources • As needed to meet RPS targets • Source: LRS data submittals and IRP information • Conventional Resources • Existing, under-construction resources • Source: 2010 LRS data submittals • Additional resources needed to meet target reserve margins • Source: LRS data submittals and IRP information

  5. Planning Reserve Margins • Source: • California – CPUC requirement (D.04-01-050) • Rest of WECC - LRS 2011 Power Supply Assessment (see table below) Set to 17%

  6. On-Peak Capacity Value • Source: Stakeholder input from 2009 and 2010 study programs

  7. On-Peak Capacity Value – Possible Adjustment • Use net qualifying capacity (NQC) for renewables as used in CPUC LTPP Cells in white have been updated with NQCs as specified in LTPP spreadsheets

  8. Firm Transfers Between Subregions • Source: CEC Summer 2011 Electricity Supply and Demand Outlook *Stakeholder input