Loraine Independent School District. High School Athletics and Renovations Construction Update November 19 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Earthwork And Building Pad Prep Is Complete
E N D
Loraine Independent School District • High School Athletics and Renovations • Construction Update • November 19, 2012
SCHEDULE STATUS • Earthwork And Building Pad Prep Is Complete • Underground Plumbing And Electrical Rough-in Is Complete In The Elementary Wing And Locker Room Areas • Underground Plumbing And Electrical Is In Progress In the Science Lab and High School Areas • Concrete Slab Has Been Poured At the Elementary Wing, And In Progress At the Gym and Locker Room Areas • Concrete Paving Is In Progress At The South Parking Area
SCHEDULE STATUS • Storm Drainage Piping At West Side Of Building is 95% Complete • Tree Removal And Building Pad Preparation Is Complete At The Bus Barn Area • Additional Lots Owned By The District Have Been Cleared
LOOKING AHEAD • The First Concrete Paving Pour Will Be Completed This Week, And Continue Over The Next Month • The Locker Room And Partial Gym Area Slab Will Be Poured In The Next Two Weeks • Underground Plumbing And Electrical Rough-in Will Continue Over The Next Month • CMU At The Gymnasium And Locker Room Areas Will Begin In Mid December