Loraine Independent School District • Campus Improvements • Construction Update • July 22, 2013
SCHEDULE STATUS • Ceiling Grid and Ceiling Tile is Complete in K-12 • Paint is Finished Except touch-up in K-12 • Ceramic Tile is Complete. • Carpet and VCT is complete. • Standing Seam Roof at Cafeteria is Completion. • Millwork is Complete. • Mechanical and Electrical Systems are Complete in K-12 • Ag. Shop Remodel is Near Completion. • Pavement and Sidewalks are Near Completion
LOOKING AHEAD • Renovations of Ag. Building will be completed. • Pavement and Sidewalks will be completed. • Canopy will be completed. [Paint, Decking, Rails] • Gym Seating will be installed. • Final Clean Commences July 22 • Furniture Arrives on July 29 • LISD Staff Occupies New Building on August 5. • Staff Training on MEP Systems and Kitchen Equipment will be on August 15. First Meal in New Kitchen Aug. 26.