Loraine Independent School District. Campus Improvements Construction Update January 21 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Underground Plumbing And Electrical Rough-in Is Complete In All Areas
E N D
Loraine Independent School District • Campus Improvements • Construction Update • January 21, 2012
SCHEDULE STATUS • Underground Plumbing And Electrical Rough-in Is Complete In All Areas • Concrete Slabs Have Been Poured In All Areas That Are Ready At This Time. • Masonry is 90% Complete In Locker Room Areas And Has Begun At The Gymnasium. • Steel Erection Is In Progress at the Gymnasium, Locker Room And JH/HS Classroom Areas • Bus Barn Concrete Has Been Poured
LOOKING AHEAD • Masonry Will Continue Over The Next Month • Steel Erection Will Continue In All Areas • Exterior Drywall Framing And Sheathing Will Begin • MEP Wall And Ceiling Rough-In Will Follow CMU And Drywall Framing • The Bus Barn Structure Will Deliver By Mid February