Loraine Independent School District • Campus Improvements • Construction Update • February 21, 2012
SCHEDULE STATUS • Gymnasium Slab is Complete • Steel Erection is Near Completion • Masonry is Complete In Locker Room Areas • CMU is Continuing at Gymnasium • Exterior Brick Veneer Has Begun • Interior and Exterior Framing is Progressing Well • Mechanical and Electrical Rough-in Has Begun • Roofing Has Begun / HS~JH~Lab is Dried-in • Bus Barn is Erected
LOOKING AHEAD • Brick and CMU Masonry Will Continue • Steel Erection Will Be Complete - Crane Will be Removed • Exterior Drywall Framing And Sheathing Will Continue • MEP Wall And Ceiling Rough-In Will Follow CMU And Drywall Framing • Steel Pans will be Erected at Gymnasium Bleachers • Concrete will be Poured at Gymnasium Bleachers • Roofing will Continue • Sheetrock Installation will Commence • Tape and Bed will Commence