Loraine Independent School District. Campus Improvements Construction Update December 17 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Underground Plumbing And Electrical Rough-in Is Complete In All Areas
E N D
Loraine Independent School District • Campus Improvements • Construction Update • December 17, 2012
SCHEDULE STATUS • Underground Plumbing And Electrical Rough-in Is Complete In All Areas • Concrete Slab Has Been Poured At The Elementary Wing, Gym, Locker Room And Junior High Classroom Areas And Is In Progress At The Science Labs, High School And Kitchen Areas • Concrete Paving Is Complete At The South Parking Area
Completed Slabs: Looking NW at Jr. High Classrooms and 1 Lab
LOOKING AHEAD • Masonry Is Scheduled To Begin December 17th • Steel Erection Is Scheduled To Begin The 2nd Week Of January • The Bus Barn Foundation Is Scheduled To Be Installed By Early January • The Kitchen, Administrative, Library And Computer Lab Areas Will Be Poured In The Next Month