An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loraine Independent School District • Campus Improvements • Construction Update • April 15th, 2013

  2. PROJECT STATUS

  3. FLOOR PLAN

  4. SITE PLAN

  5. SCHEDULE

  6. SCHEDULE STATUS • Masonry will be finishing at the end of the month. • Sheetrock is drawing to a close and Ceiling Grid is forging ahead. • Tape, Bed, Texture and Paint is concluding in the Classrooms, Corridors, Kitchen and Administration and is underway in the Gym, Cafeteria and Library Areas. • Ceramic Wall Tile is complete in the Corridors & Kitchen and is underway in the Restrooms. • Roof is dried-in and Sheet Metal work is moving forward. • Mechanical and Electrical Systems are ongoing and on track.

  7. Typical Elementary Millwork

  8. Entrance to Elementary Girl’s Restroom

  9. Typical JH/HS Millwork

  10. H.S. Boys Locker Room and Showers

  11. Coach’s Office View from Coach’s Office into Gym Trainer’s Room Film Room

  12. Library Porch

  13. Computer Lab

  14. Roof of High School Wing and South Wall of Gymnasium

  15. LOOKING AHEAD • Quarry Floor Tile will be starting this week. • Porcelain Floor Tile, VCT and Carpet will kicking off at the end of the month. • Walk-in Cooler/Freezer and Kitchen Equipment is in route. • Light Fixtures will be shipping soon. • Gym Equipment, Sports Flooring and Gym Seating will be getting underway in the coming weeks. • Fine Grading and Sidewalks will commence after completion of Masonry.