Loraine Independent School District. Campus Improvements Construction Update April 15 th , 2013. PROJECT STATUS. FLOOR PLAN. SITE PLAN. SCHEDULE. SCHEDULE STATUS. Masonry will be finishing at the end of the month. Sheetrock is drawing to a close and Ceiling Grid is forging ahead.
E N D
Loraine Independent School District • Campus Improvements • Construction Update • April 15th, 2013
SCHEDULE STATUS • Masonry will be finishing at the end of the month. • Sheetrock is drawing to a close and Ceiling Grid is forging ahead. • Tape, Bed, Texture and Paint is concluding in the Classrooms, Corridors, Kitchen and Administration and is underway in the Gym, Cafeteria and Library Areas. • Ceramic Wall Tile is complete in the Corridors & Kitchen and is underway in the Restrooms. • Roof is dried-in and Sheet Metal work is moving forward. • Mechanical and Electrical Systems are ongoing and on track.
Coach’s Office View from Coach’s Office into Gym Trainer’s Room Film Room
LOOKING AHEAD • Quarry Floor Tile will be starting this week. • Porcelain Floor Tile, VCT and Carpet will kicking off at the end of the month. • Walk-in Cooler/Freezer and Kitchen Equipment is in route. • Light Fixtures will be shipping soon. • Gym Equipment, Sports Flooring and Gym Seating will be getting underway in the coming weeks. • Fine Grading and Sidewalks will commence after completion of Masonry.