An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mobile FacilitiesLogistics Review GroupKevin SilversteinNavair Lakehurst6/27/2007

  2. TOPICS • LOADBANK • FREQUENCY CONVERTER • MF PROCUREMENT • ECU PROCUREMENT • DOD-MEP 100 & 200 TQG

  3. LOADBANK

  4. LOADBANK • PROCUREMENT • CONTRACT N68335-03-C-0228 AWARDED SEP 03 TO AVTRON, INC • PRODUCTION APPROVAL AUG 05

  5. LOADBANKLOGISTICS

  6. FREQUENCY CONVERTER

  7. FREQUENCY CONVERTER • AWARDED CONTRACT N68335-06-D-0010 TO UNITRON MAR 06 • COTS PROCUREMENT • FIVE-YEAR IDIQ CONTRACT • AUGMENT TO ECU-108

  8. FREQUENCY CONVERTER OUTPUT SPECIFICATIONS AND CAPABILITIES • Power rating: 10 kVA at 0.8 PF Lagging • Voltage: 115/200 VAC ± 1%, 3 phase • Frequency: 400 Hz • Current: 29 amps • Overload: 125% of rated load for 5 minutes 175% of rated load for 10 seconds • Efficiency: 85% minimum at full load INPUT SPECIFICATIONS • Voltage range: 120/208 VAC ± 10% • Configuration: 3 phase, wye, 4-wire, grounded neutral • Frequency range: 50 to 60 Hz • Current: 32 amps • Input current distortion: 5% maximum MECHANICAL AND ENVIRONMENTAL SPECIFICATIONS • Size: 17.5” H x 19” W x 24” D • Weight: 154 lbs. • Mounting: Rack mount • Connectors: Input - J101 is a MS3102R24-22P and mates with a MS3108R24-22S Output - J102 is a MS3102R24-22S and mates with a MS3108R24-22P • Operating temperature: -25°F to 125°F (-32°C to 52°C)

  9. FREQUENCY CONVERTERLOGISTICS

  10. MF PROCUREMENT • CONTRACT N68335-07-D-0006 AWARDED TO GICHNER SHELTER SYSTEMS NOV 06 • FIVE-YEAR IDIQ CONTRACT • MINIMIZE COST GROWTH • CRITICAL CHANGES, SIGNIFICANT COST SAVINGS • UPDATE NA19-25-177 • SEB’S, IRAC’S, TPDR’S AND ENGINEERING CHANGES

  11. MF LOGISTICS • IRACS • NA 19-25-177 IRAC NO. 7, REPAIR PROCEDURES, ISSUED June 2005, posted to NATEC • NA19-25-177 IRAC NO.8, COMPLEX-DECOMPLEX TOOL, ISSUED January 2006, posted to NATEC • MRC • NA19-600-152-6-2, to visually inspect and lubricate CDT, in-process

  12. ECU PROCUREMENT • CONTRACT N68335-06-D-0015 AWARDED TO ENVIRONMENTAL SYSTEMS APR 06 • FIVE-YEAR IDIQ CONTRACT • NEW UNITS

  13. ECU PROCUREMENT • 3 TON AND 5 TON UNIT • DIGITAL THERMOSTAT • R-134A • LIQUID CHARGE • QUICK DISCONNECT FITTINGS • ACCESS PANELS

  14. 11/8" COUPLING NUT COMPRESSOR REVERSING VALVE 1 3/8" ROTOLOCKS

  15. ECU LOGISTICS 3 TON

  16. ECU LOGISTICS 5 TON

  17. DOD-MEP 100/200KW TQG • ILS PACKAGE IN PROCESS • JOINT ARMY/NAVY/AIR FORCE • PROVISIONING (ARMY COMPLETED) • TECH MANUAL (JIL MANUAL) NA NUMBERS ARE 19-50-26, 27,28,29,30 & 31 • CADRE TRAINING – 12 - 23 JUN & 17- 21 JUL 2006 • TRAINING DATA WILL BE INCORPORATED INTO CNATT CURRICULUM

  18. DOD-MEP 100/200KW TQG

  19. DOD-MEP 200KW TQG

  20. DOD-MEP 200KW TQG

  21. DOD-MEP 100KW TQG

  22. DOD-MEP 100KW TQG