KELOMPOK PROSES DALAM MANAJEMEN PROYEK

KELOMPOK PROSES DALAM MANAJEMEN PROYEK. PENUTUPAN PROYEK. PENGAWASAN PROYEK. PELAKSANAAN PROYEK. PERENCANAAN PROYEK. BAHASAN. MEMULAI PROYEK. LAHIRNYA PROYEK. WAKTU. 9 BIDANG PENGETAHUAN YANG PERLU DIKUASAI MANAJER PROYEK

Download Presentation

KELOMPOK PROSES DALAM MANAJEMEN PROYEK

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KELOMPOK PROSES DALAM MANAJEMEN PROYEK PENUTUPAN PROYEK PENGAWASAN PROYEK PELAKSANAAN PROYEK PERENCANAAN PROYEK BAHASAN MEMULAI PROYEK LAHIRNYA PROYEK WAKTU

  2. 9 BIDANG PENGETAHUAN YANG PERLU DIKUASAI MANAJER PROYEK (SUMBER: SCHWALBE, I.T.PROJECT MANAGEMENT, THOMSON LEARNING,2006 denganmodifikasi) PIRANTI & TEKNIK MANAJM CAKUPAN PROYEK MANAJM WAKTU PROYEK MANAJM BIAYA PROYEK MANAJM MUTU PROYEK KEBU-TUHAN & HARAP-AN STAKE-HOLDER MANAJEMEN INTEGRASI PROYEK PROYEK BERHASIL MANAJM SDM PROYEK MANAJM KOMUNI- KASI PROYEK MANAJM RESIKO PROYEK MANAJM PEMBE- LIAN PROYEK BAHASAN

  3. BAHASAN Manajemenwaktu Mendefinisikankegiatan Mengurutkankegiatan Estimasisumberdaya Estimasidurasi Menyusunjadwal

  4. MANAJEMEN WAKTU PROYEK Menjaminproyekselesaitepatwaktu Proyek yang tidakselesaitepatwaktumendapatpenaltidaripemberikerja

  5. PROSES-PROSES DALAM MANAJEMEN WAKTU PROYEK KELOMPOK PROSES PERENCANAAN KELOMPOK PROSES PENGAWASAN Mendefinisikan kegiatan Mengurutkan kegiatan Mengestimasi sumberdaya kegiatan Mengestimasi durasi kegiatan Menyusun jadwal Mengendalikan jadwal

  6. PROSES 1: MENDEFINISIKAN KEGIATAN Deskripsi: Mengidentifikasi kegiatan-kegiatan tertentu yang diperlukan untuk menghasilkan berbagai serahan (deliverables) proyek sesuai persyaratan

  7. Ketersediaanpendukung Kebijakan; prosedur; pedoman yang berlaku Pernyataancakupanproyek W.B.S danpenjelasannya Rencanamanajemenproyek Masukan MENDEFINISIKAN KEGIATAN

  8. Menerapkandekomposisi Menggunakantemplate bekasproyek lain Piranti & Teknik MENDEFINISIKAN KEGIATAN

  9. HasilMENDEFINISIKAN KEGIATAN Daftarkegiatan Atributkegiatan,seperti: Daftarmilestone • identitas, • deskripsi, • kendala, • asumsi • prasyarat, • kegiatanselanjutnya, • hubunganlogikal, • leads & lags, • kebutuhansumberdaya, • dll

  10. PROSES 2: MENGURUTKAN KEGIATAN Ketergantunganterjadikarena : Alami / mandatori. Misal: pemrogramandilakukansetelahrancanganjadi Ditetapkanolehtimproyek. Misal: peran-cangandilakukansetelahhasilanalisisdisetujui steering committee untukmencegahrugi Ketergantunganpadapihakluar. Misal:instalasisetelahpenerimaanbarang Mengidentifikasidanmendokumentasikanhubunganantarkegiatanproyek.

  11. MENGURUTKAN KEGIATAN Pernyataancakupanproyek Daftarkegiatandenganatributnya Daftar milestone

  12. A B A B A B A B • Kegiatan digambarkan dengan kotak, • Panahantarkotak mewakiliketergantungan • Finish-to-start A selesai, baru B dimulai • Finish-to-finish A selesai, baru B bisaselesai • Start-to-start A mulai, baru B bolehdimulai • Start-to-finish A mulai, baru B bolehselesai • Umumnyadipakaikebutuhan finish to start

  13. d = durasikegiatan ES = earliest start time = waktuterawalkegiatandapatdimulai EF = earliest finish = waktuterawalkegiatandapatdiselesaikan LS = latest start = bataswaktu paling lambatkegiatandimulaitanpaberakibatterlambatnyaproyekselesai LF = latest finish = bataswaktu paling lambatkegiatanselesaitanpaberakibatterlambatnyaproyekselesai P D M ES EF Nama keg d LF LS

  14. Disebut juga AOA = activities on arrow, kegiatan digambarkan dengan anak panah n1 dan n2 adalahnomorsimpul (node); n1 < n2 d = durasikegiatan A D MARROW DIAGRAMMING METHOD Namakegiatan n1 n2 d n1 n2 Kegiatansemu (bukankegiatan yang sebenarnya) digambarkanuntukkeperluanmenunjukkanprasyarat; durasinya = 0

  15. ADM 4 C D 0 9 5 5 7 F 2 2 A 8 E 6 B 1 3 20 4 • Lintasan (jalur) kritis: A E • Masaproyek = 8 + 20 = 28 • Lintasan A C D F maupun B E tidakkritiskarenawaktunyakurangdari 28

  16. SOAL Diketahuiproyekdengankegiatansepertipadatabel. Buatlah : Gantt chart Diagram jaringan dg ADM Diagram jaringan dg PDM Tentukanlintasankritisnya Berapawaktutersingkatuntukmelaksanakanproyek?

  17. Gantt chart 0 5 10 15 20 25

  18. Diagram jaringandengan ADM C 2 5 6 A E 7 3 1 6 B F 10 5 D 3 4 8

  19. Tinjauanberbagailintasan: ACE= 3+6+7= 16 BDE= 10+8+7= 25 BDF= 10+8+5= 23 Lintasankritis = B D E (lintasanterlama) Proyek paling cepatselesaidalam 10+8+7 = 25 minggu 0 3 3 9 18 25 A 3 C 6 E 7 12 18 25 9 12 18 0 10 10 18 18 23 B 10 D 8 F 5 10 18 25 0 10 20 Diagram jaringandengan PDM

  20. PROSES 3: MENGESTIMASI SUMBERDAYA KEGIATAN Sumberdayaproyek: • personil • peralatan • material (langsung & taklangsung) Perluestimasikuantitasuntukmenyusun & mengontrolanggaranbiaya

  21. Pertanyaanpentingdalamperencanaan: Seberapatingkatkesulitankegiatandalamproyek? Apaadahal yang unikdalamcakupanproyek yang akanmempengaruhisumberdaya? Apapernahadaproyeksejenis? Adakejadianhistorisapa? Bagaimanaditangani? Adakah & cukupkah: SDM, alat, material ygmampu? Apaperluoutsourcingsebagianpekerjaan? Ataukahambiltenagabaru? Apaadakebijakan yang bakalberpengaruhpadaketersediaansumberdaya?

  22. MasukanMENGESTIMASI SUMBERDAYA KEGIATAN 1 Faktor-faktorlingkunganorganisasionalsepertibudaya, prasarana, SDM, dll 2 Prosedurorganisasidanaturan-aturannya (asetprosesorganisasional) 3 Daftarkegiatandanatributnya 4 Deskripsiketersediaansumberdaya Jumlah; jeniskekhususan; waktuTersedianya. 5 Rencanamanajemenproyek

  23. Menggunakanpendapat / kebijakanahli (internal ataukonsultanluar) Teknikanalisisalternatif, seperti: curahpendapat (brainstorming) Mengambil data-data yang dipublikasi MenggunakanP/Lmanajemenproyek Estimasidg pendekatandaribawahkeatas Dekomposisikankegiatanpadajadwal; Estimasikankebutuhanmasing-masingrincian; Agregasikanseluruhkebutuhansumberdaya Piranti & TeknikMENGESTIMASI SUMBERDAYA KEGIATAN

  24. 1 Kebutuhansumberdaya Penjelasantentangjenisdanjumlahsumberdayauntuksetiapelemendalam WBS Sumberdayaakandidapatdariakuisisistafataudariluar (sewa/kontrak) 2 Kalendersumberdaya (kapanbutuhapa) 3 Atribut / data tentangkegiatan 4 Strukturrincisumberdaya(RBS, resource breakdown structure) HasilMENGESTIMASI SUMBERDAYA KEGIATAN

  25. Faktorlingkunganorganisasi Prosedurorganisasidanaturan-aturannya Pernyataancakupanproyek Daftarkegiatandanatributnya Kebutuhandanwaktutersedianyasumberdaya Rencana manajemen proyek (resiko; estimasi biaya) MENGESTIMASI DURASI KEGIATAN

  26. Piranti & TeknikMENGESTIMASI DURASI KEGIATAN Pendapat/ kebijakanahli Estimasiberdasarkananalogi (top-down) . Inihanyabilakegiatanbenar-benarmiripdenganproyekterdahulu; dilakukanolehpersonil yang menguasaipersoalannya. Simulasi, misalnyadenganmenggunakanprobabilitas Analisacadanganwaktu

  27. MENGESTIMASI DURASI KEGIATAN PIRANTI DAN TEKNIK (LANJ) Analisadengandurasioptimistis, pesimistis, dan yang paling mungkin. Durasi = (O + 4 M + P)/6 O = durasioptimis M = durtasi yang kemungkinannyatertinggi P = durasipesimis

  28. Sumber: PMBOK

  29. DARI MENGESTIMASI DURASI KEGIATAN Estimasidurasikegiatan Daftarkegiatan yang mutakhirbesertaatributnya, seperti: • identitas, • kode, • deskripsi, • kendala, • prasyarat, • kegiatanselanjutnya, • hubunganlogikal, • leads & lags, • kebutuhansumberdaya, • dll

  30. PROSES 5: MENYUSUN JADWAL Deskripsi:Menetapkanjadwalrealistisproyekdenganmelakukananalisaterhadap: urutankegiatan, durasikegiatan, kebutuhansumberdayakegiatan, dan kendalapenjadwalan yang ada. Digunakanuntukmemonitorkemajuanproyekdariaspekwaktu

  31. Ketentuandanaturanorganisasi (asetprosesorganisasi) Cakupanproyek Daftarkegiatandanatributnya Diagram jaringankegiatanproyek (ADM; PDM) Kebutuhan & deskripsitersedianyasumberdaya Estimasidurasikegiatan Rencanamanajemenproyek (resiko) DALAM MENYUSUN JADWAL

  32. Piranti & TeknikDALAM MENYUSUN JADWAL Analisisjaringankegiatan CPM Pemampatanjadwal (percepatan): Crashing (meningkatkanbiaya) Fast tracking (kegiatan serial dijadikanparalelsebagian) Analisisskenariowhat-if Pengaturanleadsdanlags Perangkatlunakmanajemenproyek Model-model penjadwalan

  33. Schedule Development Tools & Techniques

  34. DARI MENYUSUN JADWAL Jadwalproyek Diagram jaringankegiatan Diagram batang (bar chart) Milestone chart Kalenderproyek Rencanamanajemenjadwal (adadalamrencanamanajemenproyek) Data model jadwal(optimis; pesimis) Permintaanperubahan Kebutuhansumberdaya yang mutakhir

  35. RENCANA WAKTU

  36. JADWAL (KALENDER)