Performance Measures x.x, x.x, and x.x. FEE and NEH XTOD Controls Installation Readiness Review November 7, 2008. Steve Lewis, Bill Abraham, Ron Shaw, Dave Kasimatis, Jim Greer, Jim Atkins.
E N D
Performance Measures x.x, x.x, and x.x FEE and NEH XTOD Controls Installation Readiness ReviewNovember 7, 2008 Steve Lewis, Bill Abraham, Ron Shaw, Dave Kasimatis, Jim Greer, Jim Atkins This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under Contract DE-AC52-07NA27344.
FEE - NEH Controls installation sequence Triple Bay ( Alcove ) Racks active to subsystems shown are highlighted. BL Instr. racks Triple Bay ( Alcove )
Subsystems • Fixed Mask, X-Ray Slit • K-Measurement Monochromator • Gas Detector/Solid-Gas Attenuator • Total Energy • Direct Imager • Off-Set Mirrors and Pop-up’s • NEH Hutches 1,2 Vacuum FEE INSTALLATION PHASE 1 FEE-NEH INSTALLATION PHASE 2
Subsystems CONTROLS READINESS • Fixed Mask, X-Ray Slit A • K-Measurement Monochromator B • Gas Detector/Solid-Gas Attenuator A • Total Energy A • Direct Imager A • Off-Set Mirrors and Pop-up’s C • NEH Hutches 1,2 vacuum C FEE PHASE 1 FEE – NEHPHASE 2
Readiness Table CONTROLS READINESS Integration at LLNL by rack Ship Date √○○
Instrument Racks under test in lab (on stands, w/doors removed). Ship first week of Jan 09 (FEE Phase 1)
Triple bay Vacuum rack under test in lab. Ship first week of Jan 09 (FEE Phase 1)
Triple bay Vacuum rack-rear view showing I/O (w/panels removed). (FEE Phase 1)
OMS Instrumentation and Beam line Vacuum Racks Loading now. Ship mid-Feb 09 (FEE Phase 2)
Facility Integration • Cable Plant Phase 5 FEE install……………complete (Ponce) • Cable Plant Phase 6 OMS prep …CAPTAR encoding (Misaki) • FEE ac power for Phase 1&2 loads……in BIO review (Khalid) • MPS requirements…….........................Mike Przybylski • Controls documentation available electronically. Hardcopy workbook on table for viewing.
Safety • Controls hardware is NRTL certified or AHJ inspected by LLNL prior to ship date. • Integrated Work Safety (IWS’) documents from LLNL are applicable to LCLS ISM ‘work basis’ for work to be performed during FEE controls installation. • Safety oversight occurs when Conv. Facilities submits vendor (MTH Engineers, Inc) electrical plans to the Bldg. Inspection Office for approval. Reviewers include Electrical, Radiation, Seismic, Environmental, Waste, and others.