1 / 9

MuTr Recap Status and Plan

MuTr Recap Status and Plan. Plan. We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp” type re- capacitation board without soldering, without taking out Station-1 chamber. Prototype re- capacitation boards are tested in RIKEN.

meryle
Download Presentation

MuTr Recap Status and Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MuTr Recap Status and Plan

  2. Plan • We are shooting for North Station-1 for post Run10 shutdown installation. • Best scenario is to mount portable “clamp” type re-capacitation board without soldering, without taking out Station-1 chamber. • Prototype re-capacitation boards are tested in RIKEN.

  3. Recap Board Prototype I

  4. Recap Board Prototype Test • Measured Electrical Contact of between probe and pad after disassembly/re-assembly of recap boards • About 50% of probes lost contact. • Problem: • Individual probe doesn’t have flexibility to absorb unique surface structure of pad Capacitor board probe pad

  5. Improvement for Prototype II • Let individual probe have flexible freedom to adjust elevation so that it can absorb surface structure (remaining solder on pad). • Rubber pad • Spring probe (Current limit < 0.2A to prevent from burning spring) • Comb shape capacitor board • Let capacitor board have more power to push probe • Thicker G10 • Angled Spring probe G10 G10 Prototype I Prototype II

  6. Conductive Silicon Rubber Pad Conductive Rubber 2~3mm thick probe pad About 30mW for 2mm thickness ~10mW for our probe size

  7. Conformal Coating and Remover Conformal coating Removed coating • Conformal coating can be removed by • “remover”. • Removed coating need to be suck up.

  8. Schedule Production cost : ~ $50k / Station-1 / Arm

  9. Installation Scenario • If “clamp” works: • Need Station-1 Scaffold • 1 hour coating removal / octant / man • 2 hours clamp install / gap / octant /man • 1 hour HV test / gap / octant /man • 1 octant/day/2men • 2 weeks + 1 week contingency = 3 total weeks • If Station-1 need to be taken out: • 2 ~ 3 months

More Related