1 / 4

THEMIS INSTRUMENT SUITE FM2/FM3 PRE-SHIP REVIEW FM4/FM5 PRE-ENVIRONMENTAL REVIEW Ron Jackson

THEMIS INSTRUMENT SUITE FM2/FM3 PRE-SHIP REVIEW FM4/FM5 PRE-ENVIRONMENTAL REVIEW Ron Jackson Mission Assurance Manager University of California - Berkeley. AS BUILT CONFIGURATION IDPU Revision levels DAP - Rev F BEB - Rev D DFB - Rev G DCB - Rev D

xiang
Download Presentation

THEMIS INSTRUMENT SUITE FM2/FM3 PRE-SHIP REVIEW FM4/FM5 PRE-ENVIRONMENTAL REVIEW Ron Jackson

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THEMIS INSTRUMENT SUITE • FM2/FM3 PRE-SHIP REVIEW • FM4/FM5 PRE-ENVIRONMENTAL REVIEW • Ron Jackson • Mission Assurance Manager • University of California - Berkeley

  2. AS BUILT CONFIGURATION • IDPU • Revision levels • DAP - Rev F • BEB - Rev D • DFB - Rev G • DCB - Rev D • PCB/FGE - Rev J • LVPS - Rev 79 • Backplane - Rev C

  3. IDPU Board Status • FM 2 & 3 • Inspected by UCB & GSFC QA • PFR’s • None open • RFA’s • Closed - We have the certificate of conformance for this part. The part meets the special requirements and procedures for Group A Inspection GSFC S-311-641 S-311-641/01. Thus, the part is qualified for flight use and there is no requirement for further testing.

  4. As-Built Flight Boards