An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Update 12 - 19 - 12

  2. Agenda • Summary Update • Current Activities Updates/Talks: • Ken Domann – Schedule/Budget Update • HowiePfeffer - Linac Modulator Prototyping

  3. Update General Info • Current Work Booster RF cavity rework : RF3 repair has started – East Gallery BRF (ALL DONE) turn-on later this week, Friday ? 3 more modulators (WG) today – 1 more to go Tuner Work : Has 1 been tested?, 2ndthis week?, 3rdnext wk Ferrite Update: Testing gig sent to vendor ; Modifying mixture for Highu LCW : Work is finished.  CUB is running okay in auto. RFQ : NTF has run treatment! Changed source yesterday – NTF Thur. HPower :NO word Booster Absorber: Stack Complete – working on finishing up face and outside Linac Modulator : EE Talk Today Booster SS: Phase matching finished Booster Modulator: Several modulators shipped – 4 modulators needed Cogging: Software work continues • Booster Shielding : Making progress on what needs to be tested and rad safety simulations and analysis. Meeting last Monday – next one in Jan. • AD FY14 & FY15 Project Labor Pow-Wow Dec 18th (All Day) – NO real news • There are questions about labor and the schedule – managers need to make sure it’s reasonable. Many managers are from support departments – but need to update RLS. Shutdown - comments (Fernanda, Todd (talk today), Mary(@review))

  4. Milestones: RFQ beam to NTF – DONE Beam to Linac Dump – DONE Beam to Booster – Mid-January!

  5. Upcoming • RLS – updates • Reports (upcoming) December 19: • December 26: Cancelled • January 16: • Alex Macridin - Simulations of Transverse Instabilities • To be scheduled: • Dave Hixson - Booster LCW Upgrades Final Report Salah Chaurize / Vladimir Sidorov - Booster Notch Absorber • PIP Talks/Lab Meetings/Management • AEM – January • Quarterly Report - January • PIP PMG – January • Dec 21 EOW